Super-large-span roof steel truss and high-altitude floor support-free construction method
A construction method and technology for steel trusses, which are applied in the directions of truss-type structures, house structure supports, house structure supports, etc., can solve the problems of complex construction measures, large amount of assembled brackets, and increased construction costs, so as to improve engineering construction efficiency and engineering. quality, solve the upper construction problems, and reduce the effect of installation difficulty
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0040] see Figure 1-6 , the present invention provides a super-long-span roof steel truss, including a roof structure and a floor slab 1, the roof structure is composed of a plurality of single trusses 3, the top of the floor slab 1 corresponds to the two ends and the middle of the single truss 3 The truss columns 2 are arranged at each place, the truss columns 2 are fixedly connected to the bottom of the single truss 3, the top of the floor plate 1 is paved with a temporary road 4, the bottom of the single truss 3 is provided with a detachable temporary support 5, two adjacent The single trusses 3 are fixedly connected by the secondary beams 6 to form a stable system, and the top between two adjacent single trusses 3 is laid with a profiled steel plate 7;
[0041]Temporary support 5, the temporary support 5 includes a positioning base 51 and a lattice column 52, the positioning base 51 is fixedly installed on the top of the floor plate 1 according to the design requirements,...
Embodiment 2
[0047] Such as Figure 7 As shown, a high-altitude floor unsupported construction method of a super-large-span roof steel truss includes the following steps:
[0048] Step S1, preparation before installation, interspersed with pre-embedded steel structure embedded parts in the superstructure civil engineering professional steel bar binding process, after the concrete pouring is completed and the curing strength meets the requirements, two 10-ton forklifts are hoisted to the floor slab with a 100-ton truck crane , Lay 2cm steel plates on the hoisting and walking routes to protect the waffle board from direct damage to the board surface;
[0049] Step S2, hoisting of the single truss 3. In step S2, the single truss 3 is arched 20mm as a whole during the installation process, and the secondary beam 6 between the truss unloading units is measured according to the actual measurement of the distance between two single trusses 3 When the height difference is less than 10mm, the inst...
PUM
Login to View More Abstract
Description
Claims
Application Information
Login to View More 


