Prefabricated installation construction method for bridge deck slab of transition section of steel plate composite beam bridge
A construction method and prefabricated installation technology, applied in the direction of bridges, bridge construction, erection/assembly of bridges, etc., can solve the problems of difficult construction quality assurance, slow construction progress, etc., to improve overall stability and installation efficiency, improve installation efficiency, The effect of reducing project cost
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0097] see Figure 1-10 , the present invention provides a technical solution: a prefabricated and installed construction method for the bridge deck of a steel plate composite girder bridge with gradual transition, which is characterized in that it mainly includes the following aspects:
[0098] 1. Technological process and key points of operation
[0099] (1) Process flow
[0100] It mainly includes the following steps:
[0101] S1: construction preparation;
[0102] S2: Template cleaning and installation;
[0103] S3: steel bar and corrugated pipe installation;
[0104] S4: concrete pouring;
[0105] S5: tensioning and grouting;
[0106] S6: lifting the bridge deck and transporting it to the storage site;
[0107] (2) Bridge deck prefabrication
[0108] mainly includes:
[0109] ① Formwork production and installation
[0110] Its specific construction process is as follows:
[0111] A. The bottom mold of the bridge deck formwork is installed on the prefabricated s...
Embodiment 2
[0178] The bridge deck of this project is customized according to the bridge deck of each gradual section, and 40 sets of templates need to be purchased according to the bridge decks of different sections. The specific combination of the templates is:
[0179] Type B: 10 sets of B1 customized formwork with L×B=(15.75m~17.25m)×3m; 4 sets of B2 customized formwork with L×B=(11.25m~15.75m)×3m; L×B=(9.75 m~11.25m)×3m B3 custom formwork 4 sets;
[0180] Type C: 4 sets of C1 custom formwork with L×B=(15.75m~17.25m)×2.5m; 4 sets of C2 custom formwork with L×B=(11.25m~15.75m); L×B=(9.75m~ 2 sets of C3 custom templates (11.25m)×2.5m;
[0181] Among them, the average single set of A-type customized formwork is 10.7t, the average single set of B-type customized formwork is 10.4t, and the average single set of C-type customized formwork is 10t. The cumulative total weight G=10.7*12+10.4*18+10*10=415.6t, According to the purchase contract price with the formwork manufacturer is 6,700 yua...