Construction method for a karst tunnel to penetrate through a high-water-level underground river and water guide structure
A technology of a water-conducting structure and construction method, which is applied in tunnels, tunnel linings, drainage, etc., can solve the problems of large water inflow in dark rivers, structural damage, and difficult control of waterproofing and drainage.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0052] figure 1 For karst tunnel according to the present invention to cross the high water level dark river construction method flow chart, below will refer to figure 1 , the construction method of the karst tunnel crossing the high water level underground river of the present invention is described in detail.
[0053] Firstly, in step 101, the underground river is surveyed, and the underground river topographic plan and typical profile are drawn.
[0054] In the embodiment of the present invention, means such as geological survey and measurement are used to confirm the trend, scale, elevation, flow rate, surrounding rock conditions, etc. of the underground river in the cave, and to draw the topographic plan and typical section of the underground river.
[0055] In step 102, a tunnel is excavated across the underground river section.
[0056] In the embodiment of the present invention, when the section of the tunnel crossing the underground river is excavated, the step-by-s...
Embodiment 2
[0080] The embodiment of the present invention also provides a karst tunnel passing through a high water level underground river water guide structure, Figure 4 It is a schematic diagram of a karst tunnel crossing a high water level dark river water guiding structure according to the present invention, Figure 5 Set schematic diagram for the water inlet of karst cave pipeline according to the present invention, Image 6 A schematic diagram is set for the water outlet of the karst cave pipeline according to the present invention, such as Figure 4-6 As shown, the karst tunnel of the present invention passes through the high water level underground river water guide structure, including the water inlet side water guide pipe 5, the upper span section water guide pipe 6, the water outlet side water guide pipe 7, the column 8, the diagonal brace 9, Beam 10, U-shaped concrete base 11, and steel flower tube 12, wherein,
[0081] The water guide pipe 5 on the water inlet side, the ...