Large-span small-clear-distance shallow-buried tunnel excavation construction method

A construction method and technology for shallow buried tunnels, applied in tunnels, tunnel linings, earthwork drilling, etc., can solve the problems of wasting equipment and human resources, affecting the construction period, and narrow working faces, so as to reduce installation and dismantling procedures and reduce excavation Cost, the effect of speeding up the excavation progress

Pending Publication Date: 2022-03-25
SOUTHERN CONSTR CO LTD OF CHINA CONSTR EIGHTH ENG DIV
View PDF0 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

The disadvantage of this method is that excavation is divided into 7 steps. The upper and lower pilot pits cannot be constructed at the same time, resulting in a narrow working surface. The left and right pilot pits need to be separated by a certain distance before they can be constructed at the same time. The pilot pits on both sides of the entrance section cannot be constructed at the same time, which wastes equipment and human resources. , which seriously affects the construction period; the surrounding rock of grade V is good, and the lithology is good, so manual excavation with excavators and woodpeckers cannot be used, and blasting excavation must be adopted. Monitor the measurement results to ensure that the temporary support can be removed only when the cave body converges and the settlement of the cave roof is stable.
Medium-conducting blasting excavation is powerful, and blasting excavation is adopted, and the temporary support small conduits, steel mesh and steel supports are severely damaged, the reuse rate is extremely low, and the cost is high

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Large-span small-clear-distance shallow-buried tunnel excavation construction method
  • Large-span small-clear-distance shallow-buried tunnel excavation construction method

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0025] The following will clearly and completely describe the technical solutions in the embodiments of the present invention with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only some, not all, embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the protection scope of the present invention.

[0026] The excavation and construction method of a large-span and small-space shallow-buried tunnel of the present invention is suitable for V-level better surrounding rock, double-hole small-space, no unfavorable geological section, no broken zone, large span, and buried depth not greater than 36m shallow buried section.

[0027] see Figure 1-2 , the present invention provides a technical solution: a method for excavating a large-span shallow-buried tunnel ...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention belongs to the field of tunnel construction, and particularly discloses a large-span small-clear-distance shallow-buried tunnel excavation construction method which comprises the following steps: determining basic mechanical parameters of surrounding rocks: testing the basic mechanical parameters of the surrounding rocks of a current construction section by carrying out an indoor test on a rock sample taken on site; after testing, according to the determined basic mechanical parameters of the surrounding rock, carrying out surrounding rock partition evolution analysis and excavation method judgment on the currently constructed section; tunnel arch advanced grouting reinforcement is carried out on the currently constructed large-span small-clear-distance segment; excavating an upper step and primarily supporting; excavating a middle step and carrying out primary support; excavating a lower step and primarily supporting; an inverted arch is excavated, and an inverted arch steel frame is installed and backfilled; and laying a waterproof plate, and completing construction after quality inspection. According to the method, an IV-level surrounding rock three-step four-step excavation mode and a V-level surrounding rock lining mode are adopted, namely, rapid excavation, strong supporting and frequent measurement are achieved, and tunnel construction safety is ensured.

Description

technical field [0001] The invention relates to the field of tunnel construction, in particular to an excavation construction method for a shallow-buried tunnel with a large span and small clear distance. Background technique [0002] The construction of long-span highway tunnels is difficult and risky. A safe, reliable and rapid excavation construction method is required. As far as the current development of highway tunnels in my country is concerned, there are relatively few shallow-buried, large-span and small-space tunnels, and there is little previous experience. At present, the excavation method of large-span tunnels with V-level surrounding rocks adopts the double-side-wall pilot pit method. [0003] The double-side-wall pilot pit method adopts three pilot pits on the left, middle and right to be excavated step by step. The pilot pits on the left and right sides are divided into upper and lower pilot pits. Excavation, a total of 7 steps. The construction method ca...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
IPC IPC(8): E21D9/00E21D11/10E21D11/18E21D11/38
CPCE21D9/00E21D9/001E21D11/10E21D11/18E21D11/38
Inventor 徐珍韦年达张南边王腾刘金强丁建忠梁铭贤
Owner SOUTHERN CONSTR CO LTD OF CHINA CONSTR EIGHTH ENG DIV
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products