Net-hanging-free plastering installation construction method for autoclaved aerated concrete batten partition wall
A technology of autoclaved gas filling and slatted partition wall, which is applied in the treatment of walls, building materials, construction, etc., to achieve the effects of saving labor costs, improving surface rigidity, and good economic benefits
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0026] Please refer to figure 1 As shown, the present invention discloses an autoclaved aerated concrete slab partition wall free-hanging net plastering installation and construction method, comprising the following steps:
[0027] S1. Obtain information and design drawings: organize technical personnel to measure and set out the wires on site, and mark the size of each part in the installation drawing, obtain more information for drawing design, and issue installation drawings;
[0028] S2. Material preparation: Plan the wall panels on site according to the drawings, draw the vertical installation diagram of the wall panels, provide the processing sheet for the factory to size and process, organize the materials to enter the site, make technical disclosures to the relevant construction personnel, and review the materials that are currently entering the site Organization inspection;
[0029] S3. Install the partition board: Before installing the wall board, the actual height ...
Embodiment 2
[0036] Please refer to figure 1 As shown, the present invention discloses an autoclaved aerated concrete slab partition wall free-hanging net plastering installation and construction method, comprising the following steps:
[0037] S1. Obtain information and design drawings: organize technical personnel to measure and set out the wires on site, and mark the size of each part in the installation drawing, obtain more information for drawing design, and issue installation drawings;
[0038] S2. Material preparation: Plan the wall panels on site according to the drawings, draw the vertical installation diagram of the wall panels, provide the processing sheet for the factory to size and process, organize the materials to enter the site, make technical disclosures to the relevant construction personnel, and review the materials that are currently entering the site Organization inspection;
[0039]S3. Install the partition board: Before installing the wall board, the actual height o...