Diving casting cast-in-place pile construction method for constructing in scree layer and sand layer

A technology of immersed tube grouting piles and construction methods, which is applied in the direction of sheet pile walls, foundation structure engineering, construction, etc., can solve the problems of reducing the bearing capacity of single piles, long cycle, and polluting the construction site, and achieve the construction period saving and bearing capacity. The effect of improving and saving costs

Active Publication Date: 2008-06-11
刘清洁
View PDF0 Cites 13 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0002] With the continuous development of industrial and civil construction, there are more and more high-rise buildings, and at the same time, different types of stratum soils are often encountered, such as pebble layers, round gravel layers, sand layers, strong weathered mudstone, etc., on such strata In the construction of high-rise buildings, due to the low bearing capacity of the natural foundation and uneven strata, percussion drilling and bored piles are usually used; however, the construction of pile foundations in the above strata has a long cycle, high cost, and difficult control of quality; In case of landslides, mud retaining technology must be used, which seriously pollutes the construction site and reduces the bearing capacity of single piles

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0011] The general situation of this embodiment is: a project has 28 floors on the ground, one floor in the basement, the foundation depth is 6.2m, and the natural foundation scheme is not established. The construction area is 47,000 square meters, and the design requires that the characteristic value of the bearing capacity of the composite foundation be greater than 560kpa. The original foundation soil is a fine sand layer. The characteristic value of the bearing capacity of the first layer of sand under the foundation is 180kpa, the number of standard penetration hits is 11-17 hits, and the thickness is 1.5-2m. The number of blows is 18-27, and the thickness is 1.8-3.5m. The characteristic value of the bearing capacity of the ③ layer of fine sand is 250kpa. The number of blows in standard penetration is 27-31, and the thickness is greater than 20m.

[0012] Adopt the method of the present invention to carry out construction, design plain concrete pile diameter Φ 350mm, pile...

Embodiment 2

[0015] The outline of this embodiment is: a certain project has 30 floors on the ground, two floors underground, and a frame-shear structure. The foundation is buried at a depth of 10 meters. The natural foundation scheme does not hold. The original geological situation is the second layer of pebble layer under the foundation, the characteristic value of natural bearing capacity is 200kpa, the thickness of this layer is 4-5.5m, and the standard penetration number is 15-25m. The strata are distributed unevenly, ③mudstone layer with a thickness of 1.5-2m. The number of strokes in standard penetration is 31-54 strokes, and the characteristic value of bearing capacity is 350kpa. ④Strongly weathered sandstone with a thickness greater than 4m.

[0016] Adopt the method of the present invention to carry out construction, design adopts plain concrete cast-in-place pile, pile diameter Φ350mm, pile length 6 meters, enter mudstone layer 1.5 meters, pile distance 1.5 meters, and the pe...

Embodiment 3

[0019] The general situation of this embodiment is: a certain project has 3 floors on the ground, 1 floor in the basement, the foundation depth is 5.8m, the column spacing is 9m×9m, and the construction area is 33,000 square meters. The design requires the use of an independent pile foundation, with a pile diameter of 450mm, a pile length of 6m, a reinforcement cage with a main reinforcement of 6Φ14, and a single pile with a vertical ultimate bearing capacity greater than 2800KN. The original foundation soil is a fine sand layer. The characteristic value of the bearing capacity of the first layer of sand under the foundation is 180kpa, the number of standard penetration hits is 11-17 hits, and the thickness is 1.5-2m. The number of blows is 18-27, and the thickness is 1.8-3.5m. The characteristic value of the bearing capacity of the ③ layer of fine sand is 250kpa. The number of blows in standard penetration is 27-31, and the thickness is greater than 20m.

[0020] Adopt the me...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention relates to a construction method for an immersed tube compaction cast-in-place concrete pile in the construction in a pebble bed, a puddingstone bed, a sand bed, and a strong weathered mudstone. Double casing pipes are hammered, simultaneously, the inner pipe is extracted from the stratum, then concrete is cast into the outer pipe, the inner pipe is positioned into the outer pipe and presses the surface of the concrete, then the outer pipe is pulled up at uniform speed, and the formation of the cast-in-place concrete pile is completed. Earth is not carried out when the hole is formed, therefore the degree of compaction of the earth among the piles is greatly enhanced, simultaneously, when the pile body concrete is cast, no hole collapse phenomenon of the outer pipe appears in the hole, even slurry wall protection is not required to be adopted, in addition, no bottom settlings exists at the bottom of the pile, thereby the characteristic that the bearing capacity of a single pile is high is ensured, and the invention has the advantages of no pollution on site and quick construction speed.

Description

technical field [0001] The invention relates to a construction method of concrete pouring piles, in particular to a construction method of sinking pipe pouring piles constructed in hard soil layers such as pebble layers and sand layers. technical background [0002] With the continuous development of industrial and civil construction, there are more and more high-rise buildings, and at the same time, different types of stratum soils are often encountered, such as pebble layers, round gravel layers, sand layers, strong weathered mudstone, etc., on such strata In the construction of high-rise buildings, due to the low bearing capacity of the natural foundation and uneven strata, percussion drilling and bored piles are usually used; however, the construction of pile foundations in the above strata has a long cycle, high cost, and difficult control of quality; In case of landslides, mud retaining technology must be used, which seriously pollutes the construction site and reduces...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): E02D5/38
Inventor 刘清洁
Owner 刘清洁
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products