Non-digging tube-pulling construction method
A technology of trenchless and construction method, applied in the field of trenchless pipe-drawing construction method, can solve the problems of inability to meet construction conditions, complicated underground pipelines, and inability to construct, achieve considerable economic benefits, reduce labor intensity, and construction speed. quick effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
example 1
[0055] Example 1. In a factory, the middle water pile number is 2+760~3+096, the pipeline length is 336m, the original design DN500 ductile iron pipe is grooved, the water surface elevation is 9.996~11.086, and the pipeline depth is 2m on average. However, the building cannot be demolished, so the site is constructed by drawing pipe. The 336m long pipe is divided into two sections, 200m is one section, and 136m is one section. The pipe material is changed to φ500PE pipe. In the process of pulling pipe construction, there was no normal business operation of the plant, and the quality of the house structure was not damaged. The construction saves 3,500 cubic meters of earth excavation and backfilling, 120,000 yuan in labor costs, and 420,000 yuan in cost. The construction period is advanced 15 days, and the project is completed and accepted.
example 2
[0056] Example 2. The reclaimed water (reclaimed water) reuse project of a plant passes through a swimming pool. The reclaimed water pile number is 3+504~3+700, the pipeline length is 196m, the high level of the flowing water surface is 9.193~9.000, and the pipeline buried depth is 3.2m on average. For pipe drawing construction, the pipe is drawn at a time of 196m. The pipe material is φ500PE pipe. Reduce the amount of earth excavation and backfilling by 2,000 cubic meters, save 80,000 yuan in personnel costs, and save 250,000 yuan in cost. The construction period is 10 days in advance, and the project is completed and accepted.
example 3
[0057] Example 3. Pipe jacking project of a sewage pipe network, stake number: 0+035~1+500, plus 300m. The main pipe is located under the slow lane of the road and is constructed by pulling pipes. The pipe material is φ500PE pipe. Save 1,900 cubic meters of earth excavation and backfill, save 80,000 yuan in labor costs, and save 250,000 yuan in cost. The construction period is 10 days ahead of schedule, and the project is completed and accepted.
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com