A pavement method for steel box girder bridge deck pavement
A bridge deck paving and steel box girder technology, applied in bridges, bridge parts, bridge construction, etc., can solve problems such as extremely high environmental temperature and humidity conditions, difficult repair of pavement materials, and inability to half-width bridge decks. Achieve the effect of improving flexural tensile stress and fatigue resistance, as well as interface shear resistance, excellent fatigue performance, and improving bridge bearing capacity
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0067] Such as figure 1 Shown, a kind of pavement method of steel box girder bridge deck pavement, it comprises the steps:
[0068] 1) Bridge deck pre-cleaning:
[0069] Clean the steel box girder bridge deck, prohibit any vehicles from passing during the construction process, and ensure that there is no soil beyond 15m at both ends of the steel box girder, so as not to pollute the bridge deck during bridge deck construction by dust;
[0070] 2) Welding shear studs:
[0071] The material and welding quality requirements of shear nails must meet the national standard GB10433-2002 and the "Technical Specifications for Highway Bridge and Culvert Construction" JTJ041-2000 on the standard design and requirements of shear nails (also known as cylindrical head welding nails). The specifications of the shear nails used is: the diameter d of the nail cap of the shear nail 1 = 10mm, the diameter of the shaft of the shear stud d 2 =14mm, the height H of the nail head of the shear nai...
Embodiment 2
[0123] Such as figure 1 Shown, a kind of pavement method of steel box girder bridge deck pavement, it comprises the steps:
[0124] 1) Bridge deck pre-cleaning:
[0125] Clean the steel box girder bridge deck, prohibit any vehicles from passing during the construction process, and ensure that there is no soil beyond 15m at both ends of the steel box girder, so as not to pollute the bridge deck during bridge deck construction by dust;
[0126] 2) Welding shear studs:
[0127] The material and welding quality requirements of shear nails must meet the national standard GB10433-2002 and the "Technical Specifications for Highway Bridge and Culvert Construction" JTJ041-2000 on the standard design and requirements of shear nails (also known as cylindrical head welding nails). The specifications of the shear nails used is: the diameter d of the nail cap of the shear nail 1 = 15mm, the diameter of the shaft of the shear stud d 2 =18mm, the height H of the nail head of the shear nai...
Embodiment 3
[0179] Such as figure 1 Shown, a kind of pavement method of steel box girder bridge deck pavement, it comprises the steps:
[0180] 1) Bridge deck pre-cleaning:
[0181] Clean the steel box girder bridge deck, prohibit any vehicles from passing during the construction process, and ensure that there is no soil beyond 15m at both ends of the steel box girder, so as not to pollute the bridge deck during bridge deck construction by dust;
[0182] 2) Welding shear studs:
[0183] The material and welding quality requirements of shear nails must meet the national standard GB10433-2002 and the "Technical Specifications for Highway Bridge and Culvert Construction" JTJ041-2000 on the standard design and requirements of shear nails (also known as cylindrical head welding nails). The specifications of the shear nails used is: the diameter d of the nail cap of the shear nail 1 = 12mm, the diameter of the shaft of the shear stud d 2 =16mm, the height H of the nail head of the shear nai...
PUM
| Property | Measurement | Unit |
|---|---|---|
| thickness | aaaaa | aaaaa |
| particle diameter | aaaaa | aaaaa |
| density | aaaaa | aaaaa |