Acid soil corrosion resisting steel used for grounding grid and preparing method of acid soil corrosion resisting steel
A soil corrosion and acid corrosion-resistant technology, applied in the field of grounding grid corrosion-resistant steel and its preparation, can solve the problems of corrosion, galvanized layer damage, loss of anti-corrosion ability, etc.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0083] Preparation of acid soil corrosion resistant steel for ground grids:
[0084] C: 0.054, Si: 0.408, Mn: 0.795, P: 0.136, S: 0.0073, Cu: 0.376, Cr: 0.537, Al: 0.302, the balance is Fe;
[0085] (1) Smelting
[0086] Melting in a 500kg vacuum induction melting furnace → casting slab;
[0087] (2) Blank opening process
[0088] Billet heating system: heating to 1100°C, holding time is 1h;
[0089] 20MPa water pressure dephosphorization;
[0090] (3) Rolling process
[0091] Heating→rough rolling→finish rolling;
[0092] Heating temperature: 1100°C, holding time: 1h;
[0093] Rolling start temperature: 1100°C, final rolling temperature 850°C, final rolling diameter 12mm.
[0094] (4) Pulling
[0095] Annealing → pickling → cold drawing, the finished product diameter is 8mm.
[0096] The obtained product was subjected to a salt spray test, and its average corrosion rate was 0.8653.
Embodiment 2
[0098] Preparation of acid soil corrosion resistant steel for ground grids:
[0099] C: 0.054, Si: 0.403, Mn: 0.7967, P: 0.137, S: 0.0073, Cu: 0.341, Cr: 0.514, Al: 0.275, the balance is Fe;
[0100] (1) Smelting
[0101]Melting in a 500kg vacuum induction melting furnace → casting slab;
[0102] (2) Blank opening process
[0103] Billet heating system: heating to 1150°C, holding time is 1h;
[0104] 16MPa water pressure dephosphorization;
[0105] (3) Rolling process
[0106] Heating→rough rolling→finish rolling→water spray cooling;
[0107] Heating temperature: 1150°C, holding time: 1h;
[0108] Rolling start temperature: 1050°C, finish rolling temperature 900°C, rolling to a diameter of 12mm;
[0109] (4) Pulling
[0110] Annealing → pickling → cold drawing, the finished product diameter is 8mm.
[0111] The obtained product was subjected to a salt spray test, and its average corrosion rate was 0.8462.
Embodiment 3
[0113] Preparation of acid soil corrosion resistant steel for ground grids:
[0114] C: 0.054, Si: 0.171, Mn: 0.500, P: 0.0071, S: 0.0044, Cu: 0.331, Cr: 3.56, Ni: 0.375, Ti: 0.020, the balance being Fe;
[0115] (1) Smelting
[0116] Melting in a 500kg vacuum induction melting furnace → casting slab;
[0117] (2) Blank opening process
[0118] Billet heating system: heating to 1100°C, holding time is 1h;
[0119] 20MPa water pressure dephosphorization;
[0120] (3) Rolling process
[0121] Heating→rough rolling→finish rolling;
[0122] Heating temperature: 1100°C, holding time: 1h;
[0123] Rolling start temperature: 1100°C, final rolling temperature 850°C, final rolling diameter 12mm.
[0124] (4) Pulling
[0125] Annealing → pickling → cold drawing, the finished product diameter is 8mm.
[0126] The obtained product was subjected to a salt spray test, and its average corrosion rate was 0.8236.
PUM
| Property | Measurement | Unit |
|---|---|---|
| Diameter | aaaaa | aaaaa |
Abstract
Description
Claims
Application Information
Login to View More 