A technology of a wind power generating set and a hoisting method, which is applied to the assembly of wind-driven engines, wind power generation, etc., can solve problems such as time-consuming, prolonged hoisting cycle, inconvenient vehicle entry and exit, etc., so as to save hoisting costs, facilitate construction operations, The effect of saving the hoisting cycle
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0031] The present invention will be further described below in conjunction with specific embodiments.
[0032] The offshore hoisting method of the ultra-compact two-blade wind power generator set in this embodiment includes the following steps:
[0033] 1) Transport the tower, main engine and blades to the vicinity of the wind turbine stand by a transport ship, waiting for hoisting, see figure 1 Shown
[0034] 2) Confirm whether the weather conditions meet the hoisting requirements: the wind speed requirements of the tower and container during the hoisting process <12.5m / s, wind speed requirements during the host installation <8m / s. If the hoisting requirements are met, start hoisting: first install the tower, clean the bolt holes and flange surface of the tower before installation, and use a level measuring instrument to detect the level of the flange at the top of the foundation ≤ 3mm. Install spreaders on the flanges at both ends of the tower, hoist the tower to the installation...