Dismantling construction method of underground mine tunnel boring machine (TBM)

A construction method and mine technology, applied in mining equipment, earthwork drilling, tunnels, etc., can solve problems affecting TBM application, difficult construction, difficult disassembly, etc., to shorten the dismantling period, shorten the project cost, improve efficiency and safety sexual effect

Active Publication Date: 2017-08-11
ANHUI UNIV OF SCI & TECH +1
View PDF4 Cites 9 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

For underground mines, the depth of burial is generally large. If a shaft is built for disassembly, the construction is difficult and the cost is too high, which makes it difficult to disasse...

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Dismantling construction method of underground mine tunnel boring machine (TBM)

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0030] The technical solutions in the embodiments of the present invention will be clearly and completely described below, obviously, the described embodiments are only some of the embodiments of the present invention, not all of the embodiments. All other embodiments obtained by persons of ordinary skill in the art based on the embodiments of the present invention belong to the protection scope of the present invention.

[0031] The present invention will be described in detail below with reference to the accompanying drawings and examples. It should be noted that, in the case of no conflict, the embodiments of the present invention and the features in the embodiments can be combined with each other.

[0032] In the description of the present invention, the terms "longitudinal", "transverse", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", " The orientations or positional relationships indicated by "top", "bottom", etc. are based on the orientat...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention provides a dismantling construction method of an underground mine tunnel boring machine (TBM). The TBM dismantling construction method comprises the following steps that (1) a dismantling roadway is built, specifically, the dismantling roadway is built in the tunneling direction in front of the TBM, and the dismantling roadway is built till reaching the parking position of the underground mine TBM; (2) dismantling preparation work is conducted, specifically, one end of the dismantling roadway is subjected to expanding excavation so that an expanding excavation section can be formed, and the expanding excavation section is tightly close to one end of a TBM tunneling roadway; and (3) TBM part dismantling construction is conducted, specifically, a TBM main machine and a TBM rear auxiliary system are disconnected firstly, the TBM main machine is driven into the expanding excavation section, and meanwhile the TBM main machine and the TBM rear auxiliary system are dismantled and conveyed onto the ground from the positions from the front and the back of the TBM. According to the dismantling construction method of the underground mine TBM, the TBM is dismantled at an underground mine, TBM dismantling is conducted from the front and the back of the TBM, small machine tools such as a monorail crane and a craning pulley are adopted, and large devices such as a gantry crane do not need to be installed under a well; and the expanding excavation and transforming engineering quantities are small, the dismantling construction period is shortened, and engineering construction cost is reduced.

Description

technical field [0001] The invention relates to the field of underground mine construction, in particular to a method for dismantling and constructing an underground mine full-face boring machine (Tunnel Boring Machine, TBM for short). Background technique [0002] In the underground mine roadway, due to the limitation of the narrow space of the underground mine, the blasting method or the cantilever type roadheader is often used to excavate the underground mine roadway. The blasting method has fewer construction machines and tools, and the construction is convenient and flexible, but the labor intensity is high, the construction risk is high, and the degree of automation is low. The size of the cantilever roadheader is small, but the excavation, slag discharge, and support are carried out step by step, so it cannot realize continuous excavation, and because of its low power, it cannot break hard rock, so it is only suitable for excavation in soft rock formations and coal se...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
IPC IPC(8): E21D9/11
CPCE21D9/11
Inventor 唐彬程桦唐永志姚直书曹承平温福平王传兵赵先发王要平程志侯俊领
Owner ANHUI UNIV OF SCI & TECH
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products