Construction process of primary lining trolley in high-risk rock tunnel and lining trolley device
A technology for lining trolleys and construction technology, applied in tunnel lining, tunnel, wellbore lining, etc., can solve problems such as slow project progress, and achieve the effect of ensuring progress and quality
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0020] The trolley for the first lining of the high-risk rock tunnel is set as the front section and the rear section, and at least three portal frames 3 are set in the front section and the rear section of the trolley for the first lining of the high-risk rock tunnel; The rear ends of the two base frames are respectively equipped with a hydraulic lifting system 2, the front parts of the two base frames are respectively equipped with a hydraulic lifting system 2, and the bottom of the hydraulic lifting system 2 is respectively equipped with a trolley traveling device 1;
[0021] Two parallel guide rails are longitudinally arranged between the upper trolley traveling device 6 and the upper part of the door frame 3, the upper trolley traveling device 6 is arranged above the front part of the guide rail, and the hoist 11 is arranged above the rear part of the guide rail; Pulley, upper trolley traveling device 6 rear end of the crossbeam middle front end and rear end respectively r...
Embodiment 2
[0026] After excavating into the construction section, when the depth is 2 meters to 2.5 meters from the end of the high molecular weight polyethylene conforming formwork 5, observe that there is no loosening of soil and rocks in the construction section, and the high molecular weight of the equipment is driven by the trolley traveling device 1 or the upper trolley traveling device 6. The polyethylene conforming formwork 5 walks into the newly excavated construction section, so that the end of the high molecular weight polyethylene conforming formwork 5 is docked with the new construction section.
Embodiment 3
[0028] After the high-molecular-weight polyethylene composite template 5 is docked with the new construction section, a concrete lining construction is performed on the tunnel wall of the newly excavated construction section through the prefabricated working window on the high-molecular-weight polyethylene composite template 5 .