Bridge incremental launching construction connecting traction system and construction method
A traction system and jacking construction technology, applied in the engineering field, can solve the problems of high construction risk, poor working environment and high cost, and achieve the effects of high construction risk, poor working environment and high cost
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0030] Embodiment of the present invention is described below in conjunction with accompanying drawing, embodiment does not constitute limitation of the present invention:
[0031] Option One:
[0032] A continuous traction system for bridge jacking construction, which is characterized in that it includes a reaction frame, a steel platform, and a jack. Two jacks 7 are arranged on the steel platform 8, and steel strands 9 are connected to the sides of the two jacks. On the reaction frame 6 , one side of the steel strand is connected with an anchor box 10 , and the anchor box 10 is arranged on the assembled beam section 1 .
[0033] The beam section includes a temporary pressure-bearing rod 4, which is a figure-eight-like structure, the lower end of which is connected to the beam section, and the upper end is connected to a steel arch. The slideway foundation and the slideway beam 3 are included under the beam section, and the slideway foundation and the slideway beam 3 include...