BZS cavity composite floor structure and construction method thereof
A construction method and technology for floor slabs, which are applied to floors, building components, building structures, etc., can solve the problems of difficult construction of gypsum mould boxes, unsatisfactory forming conditions, floating displacement of mould boxes, etc., so as to save building materials and reduce the total construction period. The effect of shortening and reducing the overall cost
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Example Embodiment
[0030] Example 1:
[0031] (1) According to the BZS cavity composite floor structure design, the provided BZS cavity composite mold box has a size of 580mm×580mm×200mm; the provided cubic concrete standard pad size is 60mm×60mm×60mm, and the pad is placed in the BZS cavity. The four corners under the cavity composite form box support the form box to facilitate the flow of concrete into the bottom of the form box, to ensure that the concrete can be vibrated and compact, and to avoid holes, honeycombs, and bar defects in the bottom of the bottom plate of the form box.
[0032] (2) Because the BZS cavity composite mold box is lighter and has better water absorption, the mason is required to water one day in advance before pouring and pour the concrete, and then water the mold box before pouring the concrete to increase the quality to prevent floating.
[0033] (3) After the installation of the BZS cavity composite mold box is completed, the anti-floating steel bars are bound according t...
Example Embodiment
[0036] Example 2
[0037] (1) According to the construction method of the BZS cavity composite floor slab, prepare the BZS cavity composite mold box, prepare for construction, and carry out the construction according to the steps in Example 1;
[0038] (2) Specific analysis and control of new points and difficulties in the construction process:
[0039] 1) When pouring and tamping, the constructor controls the size and slump of the fine concrete aggregate. The aggregate size should not be greater than 30mm, and the slump must be controlled between 180mm~210mm;
[0040] 2) The unloading workers must put the concrete between the ribs of the mold box and prevent excessive accumulation at one time;
[0041] 3) Pouring must be done in layers, using jump rib pouring, with high-efficiency vibrating, and vibrating time is sufficient. Vibrate the next place only when concrete overflows on the other side of the mold box.
[0042] (3) In order to prevent mistakes due to lack of experience, technici...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap