Porous base layer construction method of light-load road
A permeable base and construction method technology, applied in roads, roads, buildings, etc., can solve the problems of losing practical significance, simple and rough, etc., and achieve the effect of contributing to stability, ensuring durability, and facilitating repeated use
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment Construction
[0013] The present invention will be further explained below in conjunction with application examples.
[0014] The implementation steps of the present invention are as follows:
[0015] Step 1. Process a hollow prism template from wood, bamboo, PVC board or plastic bucket profile;
[0016] Step 2. Place the template evenly and spacedly on the cushion;
[0017] Step 3. Pour the base course with lean concrete or cement stabilized gravel;
[0018] Step 4. Open the top cover of the template, fill gravel to the top of the template to construct a permeable column, and then take out the template;
[0019] Step 5. Spray the infiltration column with emulsified asphalt or cement mortar;
[0020] Step 6. Fill the gaps after removing the template with medium coarse sand.
[0021] In the step 1, the height of the prism template is the same as the set base layer, and the diameter of the circumscribed circle of the horizontal cross section is 20-40 cm; in the step 2, the outer edge of the template is se...