Support method adopting steel pipe pile grouting combined with waist beams and anchor rods
A bolt support and steel pipe pile technology, which is applied in the field of support engineering, can solve the problems of large construction noise, difficulty in forming holes, and stuck drill, and meet the requirements of energy saving and environmental protection, good anchoring and reinforcement, and process simple effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0047] For a project on a plot, the foundation form is raft foundation + independent foundation + strip foundation, the structure type is frame-core tube, a public building of the first class, with a total construction area of 188,000m 2 , with a total height of 106m. The length of the foundation pit is about 201m, the width is about 101m, the maximum excavation depth is about 18.5m, and the area of the foundation pit is 21827m 2 , the average depth of the foundation pit is 17m.
[0048] The area of the foundation pit of this project is large, the soil quality of the side slope of the foundation pit is loose, the slope is small, and the on-site construction site is small, and it is impossible to excavate with a large slope. , The stability of the foundation pit slope is greatly enhanced, and the labor cost and material cost are effectively saved, which has achieved good economic and social benefits for the company.
[0049] The support of the foundation pit adopts the ...
Embodiment 2
[0067] For a project on a plot, the foundation form is raft foundation + independent foundation + strip foundation, the structure type is frame-core tube, a public building of the first class, with a total construction area of 86,000m 2 , with a total height of 136.2m. .The length of the foundation pit is about 127m, the width is about 101m, the excavation depth is about 9.7m, and the area of the foundation pit is 12827m 2 , the average depth of the foundation pit is 10m.
[0068] The backfilling of the upper part of the east side of the foundation pit is the block stone during the excavation process of the foundation pit, with a maximum particle size of about 1.2m and a content of about 60%, filled with cohesive soil; the upper part of the west part of the north side of about 5.1m is all backfilling of mixed filling soil (Miscellaneous fill is the block stone during the excavation of the foundation pit, with a maximum particle size of about 1.2m and a content of about 70...
PUM
| Property | Measurement | Unit |
|---|---|---|
| Outer diameter | aaaaa | aaaaa |
| Maximum particle size | aaaaa | aaaaa |
| Maximum particle size | aaaaa | aaaaa |