A double vanadium extraction method
A converter and molten steel technology, applied in the manufacture of converters, etc., can solve problems such as the inability to realize vanadium extraction by the double-connected converter method
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0065] Experiments were carried out in the 80-ton first converter and second converter.
[0066] Statistically, measure and calculate the liquidus temperature of semi-steel in the molten iron tank, take 1295°C, then the minimum temperature of semi-steel entering the furnace is 1305°C.
[0067] Statistics and calculation of the semi-steel temperature drop coefficient in the molten iron tank, take 0.4, and take the initial temperature of the semi-steel in the molten iron tank after the converter extracts vanadium and steel at the same time as 1360 ° C, then the maximum sedation time of the semi-steel in the molten iron tank t = (1360-1305) / 0.4 = 137.5 (min).
[0068] Take vanadium extraction period 15 (min / furnace) and semi-steel steelmaking period 23 (min / furnace), then semi-steel molten steel in the molten iron tank waits for converter semi-steel steelmaking maximum furnace number x=137.5 / (23-15)=17( furnace).
[0069] Then, when producing according to the dual vanadium ex...
Embodiment 2
[0073] Experiments were carried out in the 80-ton first converter and second converter.
[0074] Statistically, measure and calculate the liquidus temperature of semi-steel in the molten iron tank, take 1295°C, then the minimum temperature of semi-steel entering the furnace is 1305°C.
[0075] Statistics and calculation of the semi-steel temperature drop coefficient in the molten iron tank, take 0.3, and take the initial temperature of the semi-steel in the molten iron tank after the converter extracts vanadium and steel at the same time as 1360 ° C, then the maximum sedation time of the semi-steel in the molten iron tank t = (1360-1305) / 0.3 = 183.3 (min).
[0076] Take the converter vanadium extraction period of 14 (min / furnace) and the converter semi-steel steelmaking period of 21 (min / furnace), then the semi-steel molten steel in the molten iron tank is waiting for the maximum furnace number of converter semi-steel steelmaking x=183.3 / (21-14)= 26 (furnace).
[0077] The...