Problems solved by technology

[0003] The object of the present invention is to provide a design method that can reduce the design floor height of the underground garage, which adopts a beamless floor system and a beam-slab roof structure, which can effectively reduce the underground garage caused by the existing building system and pipeline layout. Excessive floor height occupies resources and increases construction difficulty. At the same time, a reserved modification position for later garage renovation is set at the edge of the underground garage, which facilitates the later renovation of the underground garage, improves adaptability, and can effectively save initial investment. , saving operation and maintenance costs

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0025] A design method capable of reducing the design floor height of an underground garage, comprising the following steps:

[0026] Step 1. Information data collection: collect the building area and location environment where the underground garage needs to be built, summarize and analyze the data, and determine the base floor height and size of the underground garage;

[0027] Step 2. Construction of the basic plan: modify the height and size of the basic layer according to customer needs;

[0028] Step 3. Determination of net height: determine the net height of the underground garage according to the construction technical requirements and construction regulations;

[0029] Step 4. Determination of floor height: Determine the final floor height of the underground garage according to the net height of the underground garage, building system and pipeline layout;

[0030] Step 5. Determination of the final scheme: According to the revised data information, the final design s...

Embodiment 2

[0038] A design method capable of reducing the design floor height of an underground garage, comprising the following steps:

[0039] Step 1. Information data collection: collect the building area and location environment where the underground garage needs to be built, summarize and analyze the data, and determine the base floor height and size of the underground garage;

[0040] Step 2. Construction of the basic plan: modify the height and size of the basic layer according to customer needs;

[0041] Step 3. Determination of net height: determine the net height of the underground garage according to the construction technical requirements and construction regulations;

[0042] Step 4. Determination of floor height: Determine the final floor height of the underground garage according to the net height of the underground garage, building system and pipeline layout;

[0043] Step 5. Determination of the reserved position: In order to facilitate the later garage transformation, ...

Embodiment 3

[0047] On the basis of the second embodiment, the underground garage also includes a parking space, a garage aisle, a floor and an anti-slip ramp.

[0048] The floor is a plain concrete floor with a thickness of 50-60, and no drainage ditches are required.

[0049] The anti-slip ramp is provided with multiple intercepting ditches and an outward flooding slope.

[0050] According to the content disclosed in the above embodiments, the newly built underground garage can effectively reduce the storey height, and at the same time, it is also convenient for the subsequent garage transformation, improves the applicability, and has broad market prospects and development potential.

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention discloses a design method capable of reducing a designed story height of an underground garage and belongs to the technical field of engineering construction. Through use of a beam-freefloor system and a beam-slab capping system, problems that resources are occupied and construction difficulties are added due to a too high story height of the underground garage caused by an existingconstruction system and existing pipeline layout can be reduced effectively; a preserved remodeling position used for later garage reconstruction is disposed at the edge of the underground garage, sothat later reconstruction of the underground garage is facilitated, adaptability is enhanced, earlier-stage investment can be effectively saved, and cost in running and maintenance is saved; and in comparison with an existing method for reducing the story height of the underground garage, the design method has wide market prospect and development potential.

Description

technical field [0001] The invention belongs to the technical field of engineering construction, and in particular relates to a design method capable of reducing the design floor height of an underground garage. Background technique [0002] At present, most of the underground garages have large structural spans and heavy loads (such as covering soil loads, civil air defense loads, fire truck loads, etc.); after considering electromechanical pipelines, structural heights, and clear heights, the floor heights of underground garages are generally large; This will result in increased earthwork excavation, increased groundwater buoyancy, increased construction difficulty and construction period, increased project construction costs, wasted resources and energy, and damaged the environment. Reducing the storey height becomes the key to energy saving and cost saving of underground garages. At present, there are some construction methods on the market that can reduce the floor hei...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): E04H6/00E04H6/10E02D29/045E04B1/00E04B5/43E04B5/48
CPCE02D29/045E04B1/0007E04B5/43E04B5/48E04H6/00E04H6/10
Inventor 郭霖江王滨陈齐腾侯森子
Owner 博维筑成设计有限公司
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products