Granular material pile construction process for treating highway diseases
A kind of construction technology, granular material pile technology, applied in the direction of roads, roads, sheet pile walls, etc., can solve problems affecting road opening to traffic, and achieve the effect of flexible construction equipment
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment 1
[0030] Embodiment 1: a kind of granular material pile construction technique of treating road disease, comprises the following steps:
[0031] A. Measure and set out; arrange the pile position plane position map according to the design and construction drawing; measure and place the points of the granular piles, and mark the points to determine the depth of the pile bottom relative to the ground;
[0032] B. Drilling: according to the measured pile position, align the drill tip center of the drilling rig with the middle point of the pile position, and adjust the level of the drilling rig and the verticality of the drill pipe through the double-sided indicator hanging on the side of the drill pipe guide frame; During the process, before each pile is constructed, technicians will check the centering and verticality of each pile, and start drilling after meeting the requirements. Observe the double-sided indicators at any time to ensure that the drilling rig does not deviate.
[...
Embodiment 2
[0047] Embodiment 2: a kind of granular material pile construction technique of treating road disease, comprises the following steps:
[0048] A. Measure and stake out; lay out the plane position map of the pile position according to the design and construction drawing; measure and place the point position of the granular material pile, mark the point position, and determine the depth of the pile bottom relative to the ground;
[0049] B. Drilling: according to the measured pile position, align the drill tip center of the drilling rig with the middle point of the pile position, and adjust the level of the drilling rig and the verticality of the drill pipe through the double-sided indicator hanging on the side of the drill pipe guide frame; During the process, before the construction of each pile, the technicians will check the pile position and verticality, and then start drilling after meeting the requirements, and observe the double-sided indicators at any time to ensure that...
PUM

Abstract
Description
Claims
Application Information

- R&D
- Intellectual Property
- Life Sciences
- Materials
- Tech Scout
- Unparalleled Data Quality
- Higher Quality Content
- 60% Fewer Hallucinations
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2025 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com