A construction method and asphalt pavement technology, which is applied to roads, roads, pavement details, etc., can solve the problems of low friction coefficient, poor skid resistance of asphalt pavement, and easy slipping of vehicles, and achieve the goal of improving skid resistance and curing strength Effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0044] see figure 1 , a kind of growing antiskid asphalt pavement construction method, comprises the following steps:
[0045] S1. Before construction, clean the base to ensure that the base is dry and clean without any loose stones, dust and impurities, and repair the pit defects existing in the base;
[0046] S2. Prepare modified emulsified asphalt on site, and add 2% of ordinary Portland cement with a strength of 42.5, and spread it on the construction road surface to form a seal;
[0047] S3. Sprinkle the penetrating layer oil on the pavement base layer, and spread the sticky layer oil between the asphalt concrete layers. After the completion, transport the mixed asphalt mixture to the site for paving. The mixing temperature of the asphalt mixture is 170°C, and the discharge The temperature is 165, the paving temperature is 160°C, the paving coefficient is 1.15, and the paving speed is 2m / min;
[0048] S4. After the paving of the upper layer is completed, a magnetic plat...
Embodiment 2
[0057] see figure 1 , a kind of growing antiskid asphalt pavement construction method, comprises the following steps:
[0058] S1. Before construction, clean the base to ensure that the base is dry and clean without any loose stones, dust and impurities, and repair the pit defects existing in the base;
[0059] S2. Prepare modified emulsified asphalt on site, and add 2.5% of ordinary Portland cement with a strength of 42.5, and spread it on the construction road surface to form a seal;
[0060] S3. Sprinkle the penetrating layer oil on the pavement base layer, and spread the sticky layer oil between the asphalt concrete layers. After the completion, transport the mixed asphalt mixture to the site for paving. The mixing temperature of the asphalt mixture is 175°C, and the discharge The temperature is 168°C, the paving temperature is 165°C, the paving coefficient is 1.15, and the paving speed is 2.5m / min;
[0061] S4. After the paving of the upper layer is completed, a magneti...
Embodiment 3
[0066] see figure 1 , a kind of growing antiskid asphalt pavement construction method, comprises the following steps:
[0067] S1. Before construction, clean the base to ensure that the base is dry and clean without any loose stones, dust and impurities, and repair the pit defects existing in the base;
[0068] S2. Prepare modified emulsified asphalt on site, and add 3% of ordinary Portland cement with a strength of 42.5, and spread it on the construction road surface to form a seal;
[0069] S3. Sprinkle the penetrating layer oil on the pavement base layer, and spread the sticky layer oil between the asphalt concrete layers. After the completion, transport the mixed asphalt mixture to the site for paving. The mixing temperature of the asphalt mixture is 185°C, and the discharge The temperature is 170°C, the paving temperature is 170°C, the paving coefficient is 1.15, and the paving speed is 3m / min;
[0070] S4. After the paving of the upper layer is completed, a magnetic pl...