Stand column prefabrication construction process

A construction technology and column technology, applied in the direction of manufacturing tools, supply devices, unloading devices, etc., can solve the problems of large waste of financial and material resources, easy pollution of the marine natural environment, high risk of construction and traffic accidents, etc., to achieve enhanced environmental protection The effect of protecting and shortening the construction period

Inactive Publication Date: 2021-06-22
ZHEJIANG COMM CONSTR GRP CO LTD +1
View PDF8 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

Among them, some bridge construction methods based on on-site concrete pouring construction mainly reflect the following problems: the ground and water area of ​​the bridge site have been occupied for a long time as a construction site, and traffic and other orders in the construction area are seriously disturbed; construction equipment and auxiliary facilities are repeatedly configured, The consumption of resources and energy is large, and the waste of financial and material resources is large; construction noise cannot be effectively controlled, construction sewage spills often occur, and surrounding residents and traffic participants complain a lot; accidental falling objects on site are inevitable, and the risk of construction and traffic accidents is high
When building a sea-crossing bridge in a marine environment with harsh weather conditions, there will be problems such as difficulty in pouring concrete on site, difficulty in ensuring construction quality and safety, high cost of fresh water transportation, and easy pollution of the marine natural environment.

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0025] In order to make the technical means, creative features, goals and effects achieved by the present invention easy to understand, the present invention will be further described below in conjunction with specific embodiments.

[0026] The present invention provides a technical solution: column prefabrication construction process, including the following steps:

[0027] Step 1: Selection of column steel bar processing equipment;

[0028] Step 2: grouting sleeve processing;

[0029] Step 3: steel bar processing;

[0030] Step 4: Auxiliary equipment installation;

[0031] Step 5: hoisting the column reinforcement skeleton;

[0032] Step 6: Processing of column steel formwork;

[0033] Step 7: Assemble the steel formwork and mold the column reinforcement skeleton;

[0034] Step 8: Install the concrete pouring platform and pour the concrete;

[0035] Step 9: Formwork removal for columns, concrete curing and storage.

[0036] In step 1, in order to ensure the processing...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

PropertyMeasurementUnit
lengthaaaaaaaaaa
diameteraaaaaaaaaa
Login to view more

Abstract

The invention provides a stand column prefabrication construction process. The stand column prefabrication construction process comprises the following steps of 1, selecting stand column steel bar machining equipment; 2, machining a grout sleeve; 3, conducting steel bar machining; 4, installing auxiliary equipment; 5, hoisting a stand column steel framework; step 6, machining a stand column sheet steel form; step 7, assembling the sheet steel form and putting the stand column steel framework into the sheet steel form; 8, installing a concrete pouring platform and pouring concrete; and 9, removing the sheet steel form and conducting concrete curing and storage. Compared with the prior art, the stand column prefabrication construction process has the following beneficial effects that the appearance quality and the inner quality of a prefabricated stand column, the accuracy of a connecting sleeve, the positioning accuracy of connected steel bars and the like are ensured, environmental protection is enhanced, the problem of labor difficulty is solved, the industrialization skills of workers are improved, and the construction period is shortened.

Description

technical field [0001] The invention is a column prefabrication construction technology, which belongs to the field of highway engineering. Background technique [0002] As the key to highways and municipal viaducts, bridges play an extremely important role. They have greatly improved the traffic network of highways and municipal viaducts, improved transportation capacity, promoted social and economic development, and brought great benefits to the majority of traffic participants. convenient. [0003] Many problems often arise in large-scale bridge construction. Among them, some bridge construction methods based on on-site concrete pouring construction mainly reflect the following problems: the ground and water area of ​​the bridge site have been occupied for a long time as a construction site, and traffic and other order in the construction area are seriously disturbed; construction equipment and auxiliary facilities are repeatedly configured, The consumption of resources...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): B28B23/02B28B13/02B28B13/06B28B11/24
CPCB28B23/02B28B13/02B28B13/06B28B11/245
Inventor 宁英杰杨延龙黄祎涵赵颖超白丽辉龚世文潘龙胜傅永刚蒋锋董鑫
Owner ZHEJIANG COMM CONSTR GRP CO LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products