Early warning treatment method for impact holing construction accident of pile foundation in karst development area
A technology of impact pore formation and development zone, applied in data processing applications, special data processing applications, instruments, etc., can solve the development characteristics of refractory karst, cannot reveal the lateral distribution and development of karst, and cannot determine the location and distribution of karst caves and fissures, etc. problems, to achieve the effect of strong guidance and easy operation
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0073] The Xueyuan Bridge in this embodiment is located in Xincheng District, Yangshuo County, Guilin City, Guangxi, with a total of 44 pile foundations designed. During the preliminary geotechnical investigation, it was found that there are large karst caves in this area.
[0074] The early warning and treatment method for pile foundation impact hole-forming construction accidents in the above-mentioned Xueyuanqiao karst development area includes the following steps:
[0075] Step 1: Geotechnical Drilling
[0076] Geotechnical drilling is carried out in the karst development area. A total of 44 exploration holes are arranged in the pile foundation survey site, numbered QK1-1~QK44-1. The drilling uses one pile and one hole, and the drilling plane is located in the center of the pile foundation. Due to the large amount of data, it is impossible to list them one by one. Taking QK3-1 as an example, the results of the drilled columnar section are shown in Table 1.
[0077] Table ...
Embodiment 2
[0101] The total length of the Peisen Liujiang Super Bridge in this embodiment is 2578.97m, and the main bridge is designed as a 145m+280m+145m prestressed concrete low-tower cable-stayed bridge, which is the largest span of the same type of bridge in Asia. The geological karst is highly developed in the Xiangzhou main pier bridge site area, the boulder overburden layer is as thick as 10m, the bedrock is relatively high and complete, and the compressive strength is high. During the investigation, it was found that 104 piles of different sizes were distributed at the location of the 24 pile foundations. , Interconnected caves. In order to ensure the smooth progress of the construction, a three-dimensional geological information model was established to guide the construction of the pile foundation.
[0102] The above-mentioned early warning and treatment method for pile foundation impact hole-forming construction accidents in the karst development area of the Xiangzhou main p...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com