Seaborne implantable rock-socketed steel pipe pile bottom sealing construction method

A construction method and technology of steel pipe piles, applied in sheet pile walls, foundation structure engineering, construction, etc., can solve the problems of increased construction costs, limited construction window period, long offshore construction period, etc., and meet the requirements of ensuring strength and compactness , shorten the offshore installation period, save the effect of renting and using

Pending Publication Date: 2021-09-24
CCCC THIRD HARBOR ENG
View PDF6 Cites 1 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0004] However, the existing construction technology needs to wait for the pile bottom concrete poured twice to reach the design strength. The offshore construction period is long, and the delay in the construction period increases the rental and use costs of the ship. At the same time, the offshore construction itself is due to the changeable sea environment. , there is a problem that the construction window period is limited, and the increase in the construction period may miss the effective construction period; furthermore, the compactness of the underwater poured concrete may not be guaranteed, and a concrete mixing ship that can adapt to sea conditions needs to be configured, which further increases the construction cost

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Seaborne implantable rock-socketed steel pipe pile bottom sealing construction method
  • Seaborne implantable rock-socketed steel pipe pile bottom sealing construction method

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0026] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the following will clearly and completely describe the technical solutions in the embodiments of the present invention in conjunction with the accompanying drawings of the present invention. Obviously, the described embodiments are part of the present invention Examples, not all examples. Based on the embodiments of the present invention, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the protection scope of the present invention.

[0027] refer to Figure 1-2 , a bottom sealing construction method of an offshore implanted rock-socketed steel pipe pile 1, the method adopts a steel casing 2, an assembled implanted core pile with a pile bottom prefabricated concrete 3, and high-performance grouting materials,

[0028] The steel casing 2 is used to drive the steel casing 2 into the seabed wi...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

A bottom sealing construction method for an offshore implantable rock-socketed steel pipe pile is characterized in that a steel casing, an assembled implantable core pile with pile bottom precast concrete and a high-performance grouting material are matched, after the steel pipe pile is manufactured, concrete is poured in a factory, the core pile is manufactured, and a plurality of distances are reserved from the bottom of the concrete to the section of the bottom of the steel pipe pile. An uneven surface in a rock-socketed formed hole can be conveniently implanted, and filling is carried out through follow-up pressure grouting high-performance grouting materials. According to the method, pile bottom concrete implanted into a core pile is prefabricated in a steel pipe pile factory, then a high-performance grouting material is used for filling and blocking a gap between the core pile and bed rock, the offshore concrete pouring construction process is omitted, the construction efficiency is greatly improved, and the construction window period is shortened. Meanwhile, the construction cost is saved, and the method has important significance on efficiency improvement and cost saving of offshore wind power socketed pile foundation construction.

Description

technical field [0001] The invention relates to the technical field of steel pipe pile installation, in particular to a bottom sealing construction method of an offshore implanted rock-socketed steel pipe pile. Background technique [0002] Wind energy is a kind of clean energy. At the same time, offshore wind energy is more abundant than that on land. my country has a long coastline, and offshore wind energy resources are abundant in coastal areas. The construction situation of rock-socketing at the steel pipe pile end of offshore wind turbine structure foundation. [0003] The general method of steel pipe pile implanted rock-socketed construction is to drive the steel casing into the seabed with a vibrating hammer, and the lower end of the casing penetrates the covering soil layer until it reaches the surface of the bedrock, and then puts the drilling machine into the steel casing , to drill the bedrock, and after the predetermined drilling depth is reached, insert the cor...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): E02D5/28E02D27/52E02D15/06
CPCE02D5/285E02D27/52E02D15/06
Inventor 潘晓炜朱国虎崔灿刘大海陶廷军阚子龙王梓秋
Owner CCCC THIRD HARBOR ENG
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products