Construction method under complex crossing condition of deep and large foundation pit and shallow-buried tunnel

A technology of shallow buried tunnels and construction methods, applied in tunnels, tunnel linings, infrastructure engineering, etc., can solve the problems of high cost and slow progress of construction period, achieve early construction time, reduce safety hazards, and ensure safety. Effect

Active Publication Date: 2021-10-01
中铁隧道集团一处有限公司
View PDF9 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0004] In order to solve the above-mentioned technical problems, the present invention aims to provide a construction method under complex intersection conditions between dee

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Construction method under complex crossing condition of deep and large foundation pit and shallow-buried tunnel
  • Construction method under complex crossing condition of deep and large foundation pit and shallow-buried tunnel
  • Construction method under complex crossing condition of deep and large foundation pit and shallow-buried tunnel

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0023] Such as Figure 2-4 As shown, a construction method under complex intersection conditions of deep and large foundation pits and shallow buried tunnels, the construction includes the main body 1 of the underground station (three floors and multiple spans), and the first underpass that is oblique or parallel to the main body 1 of the underground station 2 (double-deck double-span), the construction of the second underpass 3 (double arches) intersecting the main body of the underground station 1 and the first underpass 2 and located at the bottom of the overall intersection structure, and the first underpass 2 The bottom of is higher than the bottom of underground station body 1, comprising the following steps:

[0024] Step 1. Dividing the underground station main body 1 into an unconstructed section 102 affected by the second underpass 3 and a constructed section 101 not affected by the second underpass 3 during construction, and completing the construction of the constr...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention discloses a construction method under a complex crossing condition of a deep and large foundation pit and a shallow-buried tunnel. The construction method comprises the steps that the length and the structural shape of an open excavation section are adjusted; two groups of double spur grades are arranged to provide a deslagging channel for a second underpass, and an open excavation section of the second underpass is excavated; secondary lining construction is arranged in time after the bottom of the open excavation section is seen, and under a basic condition that the secondary lining construction of the open excavation section is met, excavation of hole bodies of underground excavation sections at the two ends is added for synchronous construction; after secondary lining of the open excavation section is completed and the strength meets the requirement, backfilling is conducted immediately, and after the backfilling strength meets the requirement, an underground station body is constructed; a hole is reserved in a triangular area at the front end of the open excavation section as a vertical shaft lifting opening; and after excavation of the hole bodies of two single holes of the underground excavation section is completed, a switching pilot tunnel is excavated at the end of a large-mileage underground excavation section. According to the method, the construction safety and quality can be guaranteed, and the problems that the construction period progress is slow and the cost is high due to "pit-in-pit" and "tunnel-in-pit" construction of a complex cross structure with the upper portion being bright and the lower portion being dark can be solved.

Description

technical field [0001] The invention relates to the technical field of tunnel construction, in particular to a construction method under complex intersection conditions of deep and large foundation pits and shallow buried tunnels. Background technique [0002] In China, the comprehensive development of the underground transportation network has become a major trend in the current situation. In urban areas, roads and tracks are often built at the same time. For the construction of new districts that are not affected by large buildings and structures, open and cut methods are often used for the construction of rail transit stations. Simultaneously carry out the construction of underground tunnels and tunnels to form large-scale and complex upper and lower cross-structure construction operations such as "pit-in-pit and tunnel-in-pit" with "upper light and lower darkness". At present, the cross structures at home and abroad are constructed according to the concept of "first down...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
IPC IPC(8): E02D17/02E02D17/04E02D29/05E21D11/10E02D17/18E02D29/02
CPCE02D17/02E02D17/04E02D29/05E21D11/10E21D11/107E02D17/18E02D29/02
Inventor 狄会杰杨轶杨晨孙晓刚刘明洪曹伟冯小涛张强
Owner 中铁隧道集团一处有限公司
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products