Steel pipe socket type tramcar prefabricated track beam and pipe pile connecting structure and construction method

A technology for trams and connecting structures, applied in infrastructure engineering, tracks, laying tracks, etc., can solve problems such as slow construction time, large manpower required, small tolerance rate, etc., and achieve short construction time and good physical properties , the effect of large tolerance rate

Pending Publication Date: 2022-05-20
SHANGHAI URBAN CONSTRUCTION MUNICIPAL ENGINEERING (GROUP) CO LTD
View PDF9 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0005] The object of the present invention is to provide a connection structure and construction method between a steel pipe socket type tramway prefabricated track beam and a pipe pile according to the above-mentioned deficiencies in the prior art. The socket connection structure of cylindrical steel pipes overcomes the problems of difficult positioning, small tolerance rate, large manpower required, and slow construction time when connecting conventional prefabricated beams and pipe piles, and realizes fast connection of sheet piles, reducing the time required for connection. Labor and time costs, and increase the structural bearing capacity of the connection through ultra-high performance concrete

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Steel pipe socket type tramcar prefabricated track beam and pipe pile connecting structure and construction method
  • Steel pipe socket type tramcar prefabricated track beam and pipe pile connecting structure and construction method
  • Steel pipe socket type tramcar prefabricated track beam and pipe pile connecting structure and construction method

Examples

Experimental program
Comparison scheme
Effect test

Embodiment

[0038] Example: The steel pipe socket tram in the present embodiment of the prefabricated rail beam and pipe pile connection structure, for achieving the connection between the hollow pipe pile 1 and the prefabricated rail beam 2.

[0039] as Figure 1 As shown, the hollow pipe pile 1 is provided with a pallet 10 inside, the pallet 10 is fixedly connected to the inner wall of the pile hole of the hollow pipe pile 1. Above the pallet 10 is poured ultra-high performance concrete 11, the ultra-high performance concrete 11 is carried by the pallet 10. Embedded in the interior of the ultra-high performance concrete 11 is a cylindrical steel pipe 6, the cylindrical steel pipe 6 is connected to the hollow pipe pile 1 by the ultra-high performance concrete 11. as Figure 5 As shown, the peripheral integral molding of cylindrical steel pipe 6 is provided with orthogonal shear nail 7, clockwise anti-shear nail 8, counterclockwise anti-shear nail 9; anti-shear nail in three different forms to ...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention relates to the technical field of constructional engineering, in particular to a steel pipe socket type tramcar prefabricated track beam and pipe pile connecting structure and a construction method.The top of a pipe pile is embedded with a cylindrical steel pipe, the bottom of a prefabricated track beam is provided with a groove matched with the cylindrical steel pipe, the cylindrical steel pipe is sleeved with the groove, and the cylindrical steel pipe is connected with the prefabricated track beam through a steel pipe; ultra-high performance concrete is poured between the groove and the cylindrical steel pipe, and connection between the prefabricated track beam and the pipe pile is achieved. The method has the advantages that the problems that when a conventional precast beam and a pipe pile are connected, positioning is difficult, the tolerance rate is small, much manpower is needed, and the construction time is short are solved, rapid connection of the sheet piles is achieved, the manpower and time cost needed during connection is reduced, and the structural bearing capacity during connection is improved through the ultra-high-performance concrete.

Description

Technical field [0001] The present invention relates to the field of construction engineering technology, in particular a steel pipe socket tram prefabricated rail beam and pipe pile connection structure and construction method. Background [0002] With the acceleration of China's urbanization construction process, the state vigorously promotes "building industrialization and housing industrialization", while meeting the green and carpet requirements of buildings, and promoting the structural adjustment and sustainable development of China's construction industry, so as to develop prefabricated concrete structures is the only way. [0003] For prefabricated concrete structures, the nodes of prefabricated components are the weak links of the prefabricated structure, and the prefabricated concrete frame structural system, the main structure of the boards and columns can be processed in the factory, as long as they are spliced on the site. Factory processing can objectively ensure t...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): E01B29/06E02D5/24
CPCE01B29/06E02D5/24
Inventor 姚青王洪新李其秦徐荣宋卿卿
Owner SHANGHAI URBAN CONSTRUCTION MUNICIPAL ENGINEERING (GROUP) CO LTD