Subsequent backfilled pea gravel concrete for lining back of tunnels and backfilling method
A tunnel and lining technology, which is applied in the direction of construction, building structure, and building material processing, can solve the problems of unfavorable backfill effect, difficult water and leak plugging, and serious grouting, so as to meet the technical requirements of backfill and stop plugging. The effect of strong water capacity and lower overall cost
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0065] This embodiment is a cast-in-place lining tunnel, the length of the backfilled tunnel is 0.6km, and the section of the tunnel is 50m 2 , the cavity between the back of the lining and the surrounding rock is 0.4-1.8m, and the amount of backfilling is 4900m 3 , take the core strength as 46MPa.
[0066] 1 Drilling, preparing the grouting head
[0067] Backfill the fine stone concrete behind the cast-in-place lining, drill an injection hole with a diameter ≥ 50 mm on the lining surface, and prepare a matching grouting head according to the diameter of the injection hole. The diameter of the grouting hole in this embodiment is 50 mm, and the diameter of the grouting head The diameter is 48mm, and the opening and closing valve is set at the grouting head, that is, a copper ball valve with a diameter of 50mm. The grouting head is an important part of the DXHB-10 multifunctional fine stone concrete pump, usually 20 spares, which can be used repeatedly.
[0068] 2. Install th...
Embodiment 2
[0078] The tunnel backfilled in this embodiment is 2km long and has a tunnel section of 13.8m 2 , the cavity between the back of the lining and the surrounding rock is 0.2-1.2m, and the amount of backfilling is 7000m 3 , take the core strength as 46MPa.
[0079] There are two differences between this embodiment and the first embodiment of the backfill method. First, this embodiment is based on the mix ratio of the backfill fine stone concrete B type, and the bulk density method is used to calculate the material. The materials are transported to the tunnel DXHB-10 multifunctional On the material platform of the stone concrete pump. According to the two groups of materials in Example 2 of backfilling fine stone concrete, add water, cement, and sand to the mixing tank of the DXHB-10 multifunctional fine stone concrete pump in turn for mixing, and the two mixing tanks work alternately to continuously supply materials. 2. At the same time as the backfilling operation, the quick-s...
Embodiment 3
[0081] The backfilled tunnel in this embodiment is 2km long and has a tunnel section of 13.8m 2 , the cavity between the back of the lining and the surrounding rock is 0.2-0.4m, and the amount of backfilling is 1184m 3 , take the core strength as 46MPa.
[0082] This embodiment is different from the first embodiment of the backfill method only in the mixing ratio of the fine stone concrete, and each group adds 200 kg of sieved pebbles with a particle size of 5-10 mm each time. In this embodiment, according to the mix ratio of backfill fine stone concrete type C, the material is prepared according to the bulk density method and transported to the material platform next to the DXHB-10 multifunctional fine stone concrete pump in the tunnel; each time the prepared backfill Raw materials, according to the two groups of materials in the third embodiment of backfilling fine stone concrete, add water, cement, sand, and stones into the mixing tank in turn, and mix evenly to form fine ...
PUM
| Property | Measurement | Unit |
|---|---|---|
| density | aaaaa | aaaaa |
| particle diameter | aaaaa | aaaaa |
| density | aaaaa | aaaaa |
Abstract
Description
Claims
Application Information
Login to View More 