Looking for breakthrough ideas for innovation challenges? Try Patsnap Eureka!

Hole drilling mudjack pile construction method

A construction method and drill pipe technology, applied in sheet pile walls, infrastructure engineering, construction, etc., can solve the problems of engineering quality, low requirements for construction machinery, difficult construction quality control, etc., to achieve low vibration and noise, construction The effect of small site and improved vertical bearing capacity

Active Publication Date: 2008-07-09
ZHEJIANG YIJIAN CONSTR GROUP +1
View PDF0 Cites 17 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

However, due to the difficulty in controlling the construction quality of its own existence, many engineering quality problems occurred in the construction of tree root pile engineering projects.
Combined with the conventional construction technology and construction management methods of tree root piles, the main reasons for the quality problems during the construction of tree root piles are as follows: (1) The construction methods of tree root piles are relatively simple, and the requirements for construction machinery are not high; (2) In the construction of tree root piles, the pursuit of construction progress and economic benefits is often too high, which makes it difficult to construct the construction quality according to the specifications; (3) The traditional tree root piles are carried out according to the technological process of forming holes → placing steel cages → putting stones → grouting construction
Among them, the grouting pipe (commonly used PVC pipe) is preset when the steel cage is lowered. After the stones are lowered, the grouting pressure is 0.1-0.3MPa. When the particle size of the stones and the grouting pressure are not well controlled, it is difficult to ensure the compactness of the grouting in the hole

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0016] After the drilling rig is positioned, level the foundation. When drilling without casing, a 1-2m long protective hole sleeve should be placed at the hole opening. Make adjustments to ensure that the orifice does not collapse. During the drilling process, the drilling rig drills according to the positive circulation process. When encountering underground obstacles, it should be drilled with a stable and reliable pilot bit at high speed and low pressure. slow. The diameter of the drill bit is equal to the designed pile diameter, and the mud retaining wall is used in the drilling process, and what is used is ordinary mud or bentonite mud. After drilling to the design depth, clear water should be used to clear the hole until the mud specific gravity is less than 1.1, if it is less than 1.25 in sandy soil, the hole should not be cleared in the clay mixed soil layer to prevent the hole from collapsing. The orifice mud should be removed in time. After clearing the hole, tak...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

A high pressure bored pile construction method of the invention belongs to the foundation piling technical field, which comprises: a drilling rig is positioned to drill a hole downward and mud protection is provided; after drilling to a required depth, using clear water for cleaning the hole; lifting a drill rod and dissembling the drill bit and inserting a reinforcement cage as soon as possible and lengthening the drill rod to the end of the hole for first hole bottom grouting; after the grouting, continuously throwing stones while in the drilling status of the drill rod; after stones are thrown in, processing the secondary hole bottom grouting and adopting concrete insertion type vibration rod for pounding to 0.6 to 1.2 m under the hole edge to ensure a dense pile top. The pile body of the invention is of concrete with no sand, has high vertical bearing ability and lateral force resistance ability. The method needs relative small construction equipment and has little construction vibration and noise, needs small construction field, can convert the foundation extension construction into the foundation extension pile construction, greatly improves vertical bearing ability of each pile, and also can process the inclined pile construction.

Description

technical field [0001] The invention belongs to the technical field of foundation piling methods, and in particular relates to a piling method for bored grouting piles. Background technique [0002] In the 1980s and 1990s, due to its wide applicability, flexible structure, low cost, and simple construction, tree root piles have been widely used in soft soil foundation reinforcement projects in coastal areas such as Zhejiang. , there are still some engineering projects using tree root pile type as the pile type of composite foundation. However, due to the difficulty in controlling the construction quality of its own existence, many engineering quality problems occurred in the construction of tree root pile engineering projects. Combined with the conventional construction technology and construction management methods of tree root piles, the main reasons for the quality problems during the construction of tree root piles are as follows: (1) The construction methods of tree ro...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): E02D5/34E02D15/04
Inventor 王伟王擎忠杜如升冯志法
Owner ZHEJIANG YIJIAN CONSTR GROUP
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products