Looking for breakthrough ideas for innovation challenges? Try Patsnap Eureka!

Deep hole underwater installation and locating method of steel pipe column in weak watery stratum

It is a technology for installation and positioning and weak ground, which is applied in the treatment of underwater structures, water conservancy projects, and building materials. It can solve the problems of complicated procedures, difficult precision, and high construction costs, and avoid the uncontrollability of loose contact. Improved work accuracy and low construction costs

Active Publication Date: 2010-09-08
CHINA RAILWAY TUNNEL GROUP CO LTD +1
View PDF4 Cites 22 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0003] In water-rich and weak formations, the ordinary steel casing retaining wall method is generally used in China to install and position steel pipe columns in deep holes drained of mud, which specifically includes the following steps: steel casing retaining wall, pumping and draining mud, and artificial hole bottom installation and positioning However, this construction method has complicated procedures, long construction period, high construction cost, high safety risk after pumping out the mud, and bored piles. The construction joints formed by pouring concrete multiple times in the interior have relatively large adverse effects on the anti-removal force of the pile, and the accuracy is not easy to measure. The specific performance is as follows:
[0004] (1) Using steel casing to protect the wall, due to the deep burial of the steel pipe column, the recovery rate of the steel casing is low, and the construction cost is high;
[0005] (2) Before manually installing the locator, the mud needs to be pumped out, and the pressure on the hole wall is relatively high. When the strength of the steel casing is lower than the pressure on the hole wall, it is easy to cause the hole wall to collapse, and there is a greater safety risk;
[0006] (3) Bored piles are generally combined with anti-removal piles, and the bottom of the steel pipe column needs to be anchored into the bored piles. The construction joints formed by pouring concrete multiple times have a relatively large adverse effect on the anti-removal force of the bored piles;
[0007] (4) Concrete needs to be poured multiple times, with complicated procedures and long construction period;
[0008] (5) After positioning and installation, the process of pouring concrete is not easy to control;
[0009] (6) When the steel pipe column is installed, the contact degree between the locator and the steel pipe column directly affects the verticality of the steel pipe column, but the contact degree is not easy to detect

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Deep hole underwater installation and locating method of steel pipe column in weak watery stratum
  • Deep hole underwater installation and locating method of steel pipe column in weak watery stratum
  • Deep hole underwater installation and locating method of steel pipe column in weak watery stratum

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0044] The present invention can be explained in more detail with reference to the following examples; however, it should be noted that the present invention is not limited to the following examples.

[0045] combined with Figure 2~4 The installation and positioning method of the steel pipe column in the deep hole underwater in the water-rich and weak stratum firstly pours concrete 6 of a certain height in the steel pipe column 7, and then installs it; The mud 9 and the buoyancy in the concrete in the bored pile 3, the second is to use the concrete 6 in the steel pipe column to block the mud 9 in the bored pile from entering the steel pipe column 7, and provide conditions for the construction workers 5 to locate the middle and lower parts of the steel pipe column 7; and The steel pipe column 7 is installed by a two-point positioning method, one point is located on the ground surface, and one point is located in the hole of the bored pile 3; the ground surface uses a positioni...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a deep hole underwater installation and locating method of a steel pipe column in a weak watery stratum, concretely comprising the following construction steps of firstly, pouring concrete with a design height in the steel pipe column, and installing and locating a screw jack at the bottom of the steel pipe column; secondly, measuring and paying off on the construction ground surface, and drilling by a drill; thirdly, installing a drilling pile reinforcement cage in a hole; fourthly, installing a location platform on the construction ground surface; fifthly, hoisting the steel pipe column and putting the steel pipe column in a drilling pile hole; sixthly, locating the top part of the steel pipe column by the ground surface location platform; seventhly, locating and measuring the verticality of the steel pipe column by a laser plummet; eighthly, locating the bottom of the steel pipe column by the screw jack; ninthly, pouring drilling pile concrete underwater to the design burying height of the steel pipe column; and tenthly, pouring steel pipe column internal concrete to the top of a steel tube after the drilling pile internal concrete achieves the design strength of 70 percent. The method has the advantages of simple operation, high construction efficiency, low construction cost, high and controllable installation accuracy and little safety risk.

Description

【Technical field】 [0001] The invention relates to an installation method of a vertical load-bearing system in a cover-excavation construction structure, in particular to an installation and positioning method of a steel pipe column in a deep-hole underwater in a cover-excavation reverse construction structure. 【Background technique】 [0002] With the rapid development of China's economy and the acceleration of urbanization, urban construction has entered a period of great development, and the enthusiasm for construction in various places is increasing day by day. However, increasingly prosperous cities create less and less conditions for construction and leave less and less time for construction. Construction is difficult. getting bigger. The above phenomena are mainly reflected in: large project scale, many foundation pit groups, large foundation pit area and deep depth. It is known that the cover-excavation method is to build the enclosure structure and intermediate piles...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): E04G21/14E04G21/16E02D29/045
Inventor 李建高汪立辉李少利胥明石清虎田双龙袁甲
Owner CHINA RAILWAY TUNNEL GROUP CO LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products