[0014] Such as figure 1 with figure 2 As shown in the figure, 1 is the wall of the tube, 2 is the roof of the tube, 3 is the pole steel beam, 4 is the wedge, and 5 is the steel pipe truss.
[0015] The present invention relates to a construction method for the roof of a conjoined barrel warehouse, which comprises:
[0016] 1. Set up a shoulder pole steel beam on the wall of the cylinder
[0017] The construction should be planned before the construction of the silo wall 1, and the opening of the steel beam should be reserved in the wall in advance. The rigid operating platform should be lowered and completed before construction, and the installation of the steel beam should be carried out on the sliding form platform.
[0018] The shoulder pole steel beam 3 is constructed by [12]. The channel steel is arranged along the arc direction of the cylinder wall @1.5m, and at the same time, it is suitable for the size of each rigid operating platform (1.5m wide). The steel b...