Construction method of grouting bored pile after self-circulation
A technology of bored piles and construction methods, applied in the direction of sheet pile walls, foundation structure engineering, construction, etc., can solve the problems such as mud pollution of the environment, achieve the effects of saving soil and water resources, improving bearing capacity, and reducing pollution
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1)
[0048] See Figure 1 to Figure 4 , the self-circulation post-grouting bored pile construction method of this embodiment is suitable for the construction of bored piles with large construction sites and high requirements on pile body quality.
[0049] The self-circulation back grouting bored pile construction method of the present embodiment mainly includes the following steps:
[0050] ① Determining the pile position and drilling rig positioning:
[0051] Step 1: Measure and place the axis, pile position and elevation control points according to the drawing according to the general plan, coordinates and elevation datum points provided by the owner;
[0052] Step 2: Number each pile according to the pile location map, and control the coordinates according to the general plan, turn over the pile location coordinates of each pile one by one, use the total station to stake out on the spot, and hang the stakeout points on the spot Pile number plate;
[0053] Step 3: Retest the p...