Looking for breakthrough ideas for innovation challenges? Try Patsnap Eureka!

Well point plastic draining pipe type vacuum preloading seepage consolidation and dewatering preloading power consolidation combined method

A dynamic consolidation and well point technology, applied in infrastructure engineering, soil protection, construction, etc., can solve the problems of low strength of pvc sealing film, poor preloading effect, difficult construction of sealing film, etc., to reduce post-construction The effect of residual settling

Active Publication Date: 2016-09-28
CABR FOUND ENG CO LTD
View PDF5 Cites 4 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0004] 1. The construction of large-area sealing membranes is difficult, and vacuum preloading on land requires a lot of manual laying of membranes with a low degree of mechanization, especially the construction of underwater vacuum preloading sealing membranes is more difficult;
[0005] 2. The PVC sealing film has low strength and is easy to be damaged and leak air. The cost of the second layer of sealing film and the first layer of geotextile is high, and it is difficult to find the air leakage point;
[0006] 3. A large number of PVC sealing films are not environmentally friendly;
[0007] 4. The surface under the film can reach a maximum negative pressure of 80kPa, and the negative pressure transmission loss to the deep part of the soil layer is fast. Generally, the loss of negative pressure per meter to the deep part is about 10kPa. The effective reinforcement depth is shallow;
[0008] 5. The loading surface is on the original ground surface or the backfilled land surface. Even if the surface sealing film does not leak, the slow air leakage of the shallow soil around the reinforcement area cannot be ignored, especially in the case of long-term loading for about 90 days, when the groundwater level drops to The degree of air leakage in shallow soil around a certain degree of reinforcement area is even more worrying
[0009] 2. The improved vacuum preloading reinforcement has the following disadvantages:
[0010] 1. The sand-removing cushion layer is changed to the mode of direct connection of plastic slabs with hand-shaped joints, and the mode of indirect negative pressure transmission is changed to direct negative pressure transmission mode, but it still needs a sealing film, and the maximum negative pressure loading surface is still on the surface;
[0011] 2. The sealing layer is formed by blowing and filling mud, or the vacuum branch pipe is directly connected to the plastic discharge into the soil for about 1.5 meters, or the vacuum filter tube is about 3 meters underground, and the side blister row replaces the sealing film. The dredging fill mud loses water, consolidates and cracks, the groundwater level drops rapidly, and the sealing effect is greatly reduced;
[0012] 3. The ultra-soft soil for land reclamation cannot be mechanically constructed. First, artificially insert the shallow layer of plastic drainage vacuum preloading, and then do deep vacuum preloading after the foundation strength is suitable for mechanical construction. The principle and process of conventional vacuum preloading are almost the same, only the simple difference between manual and mechanical, the process is more complicated, the cost is high, and the efficiency is low;
[0018] For traditional main pipes and branch pipes, submersible pump gravity dewatering is used for tube wells, and a combination of submersible pump gravity dewatering and vacuum dewatering is used for deep well dewatering. The spacing between well points is larger, generally 15*15m. The coarse and sparse treatment method focuses on precipitation. If the spacing is too large and the time is short, it cannot simultaneously have the effect of vacuum preloading and negative pressure consolidation;
[0019] Coarse and sparse distribution of genetic precipitation and short-term (about 30 days) treatment methods in the precipitation dynamic compaction treatment are only suitable for shallow treatment;

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Well point plastic draining pipe type vacuum preloading seepage consolidation and dewatering preloading power consolidation combined method
  • Well point plastic draining pipe type vacuum preloading seepage consolidation and dewatering preloading power consolidation combined method
  • Well point plastic draining pipe type vacuum preloading seepage consolidation and dewatering preloading power consolidation combined method

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0107] Basic information before foundation treatment:

[0108] The third layer of muddy clay layer of the foundation has a water content of 55%, a compressive modulus of 2.3MPa, an average layer thickness of 15 meters, a buried depth of 5 meters at the top of the layer, and a buried depth of 20 meters at the bottom.

[0109] Implementation steps:

[0110] Step 1. The site is leveled, and drainage ditches are excavated around the area to be reinforced;

[0111] Step 2. Pre-tamping, energy level 800kN.m, square tamping point spacing 4m*4m, after tamping, construct cement mixing pile lateral sealing retaining wall or mud lateral sealing retaining wall;

[0112] Step 3. Arrangement of integrated well point plastic exhaust vacuum system

[0113] 3.1. The integrated well point plastic pipe is inserted and constructed to form an integrated well point plastic pipe grid;

[0114] The grid spacing of the integrated well point plastic pipe grid is 1.2m, and the insertion depth of the ...

Embodiment 2

[0130] Basic information before foundation treatment

[0131] The fourth silty clay layer of the foundation has a water content of 38%, a compressive modulus of 3.8 MPa, an average thickness of 13 meters, a buried depth of 3 meters at the top of the layer, and a buried depth of 16 meters at the bottom of the layer.

[0132] Step 1. The site is leveled, and drainage ditches are excavated around the area to be reinforced;

[0133] Step 2. Do not carry out pre-tamping before precipitation, and construct lateral sealing retaining wall of cement mixing pile or lateral sealing retaining wall of mud;

[0134] Step 3. Arrangement of integrated well point plastic exhaust vacuum system

[0135] 3.1. The integrated well point plastic pipe is inserted and constructed to form an integrated well point plastic pipe grid;

[0136] The grid spacing of the integrated well point plastic pipe grid is 1.5m, and the insertion depth of the integrated well point pipe is 16m

[0137] The length of ...

Embodiment 3

[0152] Basic information before foundation treatment

[0153] The silty clay in the second layer of the foundation has a water content of 78%, a compressive modulus of 2.1 MPa, an average thickness of 20 meters, a buried depth of 4 meters at the top of the layer, and a buried depth of 24 meters at the bottom of the layer.

[0154] Step 1. The site is leveled, and drainage ditches are excavated around the reinforcement area;

[0155] Step 2. Pre-tamping before precipitation, energy level 600kN.m, square tamping point spacing 4m*7m, after tamping, construct cement mixing pile lateral sealing retaining wall or mud lateral sealing retaining wall;

[0156] Step 3. Arrangement of integrated well point plastic exhaust vacuum system

[0157] 3.1. The integrated well point plastic pipe is inserted and constructed to form an integrated well point plastic pipe grid;

[0158] The grid spacing of the integrated well point plastic pipe grid is 1.0m, and the insertion depth of the integrat...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention relates to a well point plastic draining pipe type vacuum preloading seepage consolidation and dewatering preloading power consolidation combined method. The method is characterized by comprising the following steps: levelling a site, and draining an area to be reinforced; then determining to carry out or not carry out pre-tamping before dewatering; arranging an integrated well point plastic draining pipe vacuum system; performing vacuum preloading, namely, constructing dams of cofferdams around the area to be reinforced, and pumping water from a water source in the periphery of the area to be reinforced into the cofferdams around the area to be reinforced, and then carrying out vacuum preloading, wherein underground water is completely pumped and returned to the surface of the area to be reinforced during the vacuum preloading; performing vacuum dewatering preloading, namely, forming openings in the constructed dams of the cofferdams to drain water stored in the dams of the cofferdams, and carrying out vacuum dewatering preloading at a plurality of times, wherein light tamping is carried out between every two adjacent vacuum dewatering preloading processes, and full tamping is carried out after the last vacuum dewatering preloading; finally, vibrating and rolling in the whole site, then measuring the elevation, and handing over the completed project. The method has the advantages of being simple to operate, low in cost, and good in construction effect.

Description

technical field [0001] The invention relates to a soft ground treatment method, in particular to a well point plastic drainage vacuum precompression seepage consolidation combined with precipitation precompression dynamic consolidation method. Background technique [0002] According to 7.1.1 of the "Code for Design of Building Foundations" (GB5007-2011), weak foundations refer to foundations mainly composed of silt, muddy soil, flushing soil, miscellaneous filling soil or other highly compressive soil layers. Before building construction on the weak foundation, it is necessary to consolidate the weak foundation first. The conventional consolidation treatment methods are as follows: [0003] 1. Conventional vacuum preloading reinforcement. Conventional vacuum preloading reinforcement "on land and under water in rivers, seas, lakes and swamps" soft soil foundations all need to be laid with sealing film and sand cushion, but there are the following disadvantages: [0004] 1. T...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): E02D3/10E02D3/046E02D19/10
CPCE02D3/046E02D3/10E02D19/10
Inventor 张禹
Owner CABR FOUND ENG CO LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products