A construction method of inclined steel pipe combined with cement and soil to form a force-bearing body
A construction method and cement-soil technology, which can be applied in basic structure engineering, construction, sheet pile walls, etc., can solve the problems of reduced bearing capacity of stressed bodies, difficulty in forming cement-soil enlarged bodies, and filling, etc., and achieve a simple and fast construction method. Effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0022] Embodiment 1: This embodiment specifically relates to a construction method in which an inclined steel pipe is combined with cement and soil to form a force-receiving body. The construction method includes the following steps:
[0023] (1) if figure 1 As shown, the drilling rig 1 is moved to the position to be constructed. The drilling rig 1 is a mixing pile drilling rig. Adjust the inclination angle between the drill pipe 2 and the ground to meet the design requirements; after the angle adjustment is completed, start the drill pipe 2 to move into the soil Oblique drilling into the hole;
[0024] (2) if figure 1 As shown, after the mixing head 3 at the front end of the drill pipe 2 is drilled to the design depth, the drill pipe 2 continues to drill for a certain distance, and at the same time, the cement slurry is sprayed outward through the mixing head 3, and the cement slurry is mixed with the stirring head 3 The mud is mixed to form an obliquely uniform cement-soil...
Embodiment 2
[0028] Embodiment 2: as figure 2 As shown, this embodiment specifically relates to a construction method in which inclined steel pipes are combined with cement and soil to form a force-receiving body. Corresponding spray holes are distributed on the drill bit at the end of the rod 2. When the drill rod 2 is drilled to the design depth in the soil, the end of the drill rod 2 starts to spray cement slurry, that is, high-pressure rotary jet drilling, so that the cement slurry It is mixed with the mud to form a section of cement-soil expansion body 4 with uniform oblique direction, and the diameter of the cement-soil expansion body 4 is greater than the diameter of the borehole.
[0029] The construction methods of the remaining steps in this embodiment are the same as those described in Embodiment 1, so they will not be repeated here.