Dismantling Method of Main Girder of Overspan Existing Line Bridge
A technology for existing lines and bridges, which is applied in the field of dismantling the main beams of upper-span existing line bridges to achieve the effects of simple construction, reasonable structural design, and simple hoisting system structure.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0061] Such as figure 1 A method for dismantling the main girder of a bridge spanning an existing line is shown. The main girder of the bridge to be dismantled is a main girder spanning the existing railway line. A plurality of beam sections 14 to be removed have the same structure and are all reinforced concrete beam sections. The beam sections 14 to be removed are assembled from M reinforced concrete T beams 15 from left to right, wherein M is a positive integer and M≥3; the front and rear ends of the beam section 14 to be removed are respectively supported on a supporting pier, and the bridge deck pavement layer is laid on the beam section 14 to be removed; for any beam section 14 to be removed When carrying out the demolition construction of the whole group, the following steps are included:
[0062] Step 1, bridge deck pavement milling: milling the bridge deck pavement on the currently constructed beam section;
[0063] The currently constructed beam section is the curr...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com