Looking for breakthrough ideas for innovation challenges? Try Patsnap Eureka!

Construction method for reverse direction underground excavation of large inclination-angle escalator passage in thin-layer crushed hard rock stratum

A technology of rock formation and construction method, applied in tunnels, tunnel linings, underground chambers, etc., can solve problems such as difficulty in ensuring safety in use and operation, frequent excavation disturbances, narrow working space, etc., and achieve economic and social benefits Significant, less disturbance times, strong operability

Active Publication Date: 2017-09-15
CHINA RAILWAY CONSTR BRIDGE ENG BUREAU GRP
View PDF5 Cites 5 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0003] Escalator passages are generally set up in areas with special functions, dense flow of people and goods, and large traffic flow. During the construction of underground escalator passages, due to unfavorable factors such as complex geological conditions, many surface structures, and pre-buried depths, the traditional positive step method is used for construction. There are many times of excavation disturbance, and it is difficult to guarantee the use and operation safety of ground traffic and existing structures. Although the safety factor of side wall pilot pits is high, it is limited to the current excavation section of escalator passages. Unfavorable factors such as narrow space, low construction efficiency, slow progress, and high cost

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Construction method for reverse direction underground excavation of large inclination-angle escalator passage in thin-layer crushed hard rock stratum
  • Construction method for reverse direction underground excavation of large inclination-angle escalator passage in thin-layer crushed hard rock stratum
  • Construction method for reverse direction underground excavation of large inclination-angle escalator passage in thin-layer crushed hard rock stratum

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0066] This embodiment is further optimized on the basis of the above embodiments, such as Figure 1-Figure 3 As shown, the reverse direction underground excavation construction method of the escalator channel with a large dip angle in the thin-layer broken hard rock stratum includes the following construction steps:

[0067] Step S1: construction preparation;

[0068] Step S2: Construction of the lower pilot tunnel; the lower pilot tunnel includes an upper step and a lower step; the upper step includes I zone 1 and III zone 3, and the I zone 1 includes the first support area 11 and the second support District 12; the lower steps include II District 2, and the II District 2 includes the third support area 23 and the fourth support area 24; specifically include the following construction steps:

[0069] Step S21: advance support; to reduce vibration and dust, the excavation cycle footage is controlled at 0.8-1.0m;

[0070] Step S22: Excavation in Zone I 1 and support in the f...

Embodiment 2

[0087] This embodiment is further optimized on the basis of the above embodiments, such as Figure 1-Figure 3 As shown, further, in order to better realize the present invention, the step S22 specifically includes the following steps:

[0088] Step S22: After the blasting operation is completed, the slag is removed, and the rock face is sealed with C25 concrete plain spray;

[0089] Step S222: Erection of a steel frame, supporting with anchors, nets, and spray systems;

[0090] It should be noted that, through the above improvements, after the blasting operation is completed, the slag is removed, and the rock surface is sealed with C25 concrete plain spray; steel frames are erected, and anchors, nets, and spray systems are supported; The initial support steel frame is equipped with 4 locking foot grouting anchor pipes. Two of the grouting anchor pipes are inclined at 7-10° and two are inclined at 10-20°. They are set in pairs. The anchor pipes are embedded in 100cm long and 2...

Embodiment 3

[0093] This embodiment is further optimized on the basis of the above embodiments, such as Figure 1-Figure 3 As shown, further, in order to better realize the present invention, the step S23 specifically includes the following steps:

[0094] Step S231: After the excavation of the upper step is 5-6m ahead of time, the lower pilot tunnel and the lower step will follow up in time; The stagger distance is not less than 2m, and the footage of each excavation is controlled within 2 steel frames, that is, not more than 1.6m. Operator operation;

[0095] Step S232: After the excavation, use C25 concrete spraying to seal the rock surface;

[0096] Step S233: Then set up a steel frame, and carry out anchor, net and spray system support. At the arch feet on both sides of the lower steps, corresponding to each primary support steel frame, four locking-foot grouting anchor pipes are installed. For setting, the anchor pipe is embedded with 100cm long and 25m diameter threaded steel ba...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a construction method for reverse direction underground excavation of a large inclination-angle escalator passage in a thin-layer crushed hard rock stratum. The construction method comprises the following construction steps of S1, construction preparation, S2, lower pilot tunnel construction, S3, upper pilot tunnel construction, S4, deslagging and forming, and S5, construction of a bottom plate and second lining concrete. The construction method for reverse direction underground excavation of the large inclination-angle escalator passage in the thin-layer crushed hard rock stratum has the beneficial effects that reverse direction excavation is used, thus the disturbance time is less, and a support structure is stable, safe and reliable; the construction processes such as a single side-wall pilot tunnel method, a double side-wall pilot tunnel method and a bench method are combined scientifically, and the conflict between safety and the progress is handled effectively; the construction speed is high, the construction cost is low, the influence on the ground surface environment and an existing building is small, and economic benefits and social benefits are significant; and practicability and operability are high.

Description

technical field [0001] The invention relates to the technical field of tunnel process construction, in particular to a reverse-direction underground excavation construction method for a large dip-angle escalator channel in a thin-layer broken hard rock stratum. Background technique [0002] With the continuous development of social economy and the rapid advancement of urban construction, escalator passages are used more and more in vertical transfer stations, and are developing in the direction of multi-functionality. [0003] Escalator passages are generally set up in areas with special functions, dense flow of people and goods, and large traffic flow. During the construction of underground escalator passages, due to unfavorable factors such as complex geological conditions, many surface structures, and pre-buried depths, the traditional positive step method is used for construction. There are many times of excavation disturbance, and it is difficult to guarantee the use an...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): E21D9/02E21D11/00E21D11/10
CPCE21D9/02E21D11/00E21D11/10
Inventor 苏春生张庆何十美梁朋刚
Owner CHINA RAILWAY CONSTR BRIDGE ENG BUREAU GRP
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products