Bottom sealing method of high pile cap steel suspension box applied to long-period wave surge conditions
A high-pile cap and long-period technology, applied in caissons, buildings, bridge construction, etc., to solve the effect of water seepage and corrosion of steel bars
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0038] Embodiment 1 is applied to the high pile cap construction case of the China-Maldives Friendship Bridge in the Indian Ocean. The China-Maldives Friendship Bridge is the first sea-crossing bridge in the Indian Ocean, connecting the capital of Maldives and the airport island. The main bridge is a five-span V-shaped pier rigid frame bridge with a total length of 760m. The main piers 19#~23# are located in the deep sea area, using high-pile cap foundations, taking the 21# middle pier as an example, the cap is a 7-pile shuttle structure, the thickness is 5m, the bottom elevation of the cap is -3.0m, and the maximum pile length is 104m , the cantilever height above the seabed is 40m, the normal water level is +0m, the water level change caused by the tide is about 1m, the design maximum flow velocity is 1.5m / s, the most unfavorable swell period exceeds 14s, the maximum wavelength is 50m, and the maximum wave height is 4m. The wave height in the window period is about 1-1.5m. l...
PUM
Login to View More Abstract
Description
Claims
Application Information
Login to View More 