Stiffening device for bridge pier and abutment foundation and implementation method of stiffening device
An implementation method and basic technology, applied in the direction of infrastructure engineering, construction, etc., can solve the problem of weak resistance to overturning damage of open-cut foundations, and achieve the effect of short construction period
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment approach
[0029] refer to Figure 1 to Figure 3 , the present invention is a kind of implementation method that is used for the stiffening device of bridge abutment foundation, comprises the following steps:
[0030] Step 1: Drill the hole according to the predetermined position. The hole depth is the same as the depth of the screw rod, and the hole diameter is 3-15mm larger than the screw rod. The drill hole is drilled with an electric hammer impact drill, and the surface of the hole has sufficient roughness;
[0031] Step 2: Use a hard bristle brush to clean the floating skin on the hole wall, and then use an air compressor to blow off the dust and rock debris in the hole, while ensuring that the hole is dry;
[0032] Step 3: Use mortar or colloid to start injecting from the bottom of the hole until 2 / 3 of the hole is filled. After inserting the screw, the mortar or colloid will fill the entire hole;
[0033] Step 4: Slowly screw the screw into the hole to the bottom of the hole, rem...