technical field
[0001] The invention belongs to the technical field of highway bridge construction, relates to a construction method of a steel-concrete composite beam for a bridge, and is applied to the construction field of the superstructure of a bridge steel-concrete composite beam in highway engineering. Background technique
[0002] Steel-concrete composite beams have large spans and strong bearing capacity, and are often used in flyover bridges, ramp bridges and municipal roads. During the construction of steel-concrete composite beams, the construction method of first hoisting the steel girders and then the overall cast-in-place concrete bridge deck is adopted. The steel beam hoisting process is divided into whole-hole hoisting and segmental hoisting. Segmental hoisting equipment generally uses gantry hoisting. Machine, high construction safety risk, low efficiency, the hoisting of the whole hole needs to set up temporary buttresses, set up floor brackets, cooperate ...