Construction Method of Loess Tunnel Through Landslide

A technology for loess tunnels and construction methods, which can be applied to tunnels, earthwork drilling, tunnel lining, etc., and can solve the problems of high moisture content of new loess, stratum subsidence, and tunnel structure damage.

Active Publication Date: 2021-02-05
CHINA RAILWAY 20 BUREAU GRP CORP LTD
View PDF5 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0006] The construction of the entrance section of the loess tunnel passing through the landslide is very difficult, especially when the entrance section of the tunnel is located in the front of the landslide, the construction difficulty is even greater. After analysis, the main problems are as follows: Inducing the sliding of the landslide body can easily bring safety hazards and interference to the tunnel construction; second, the tunnel entrance (ie, the tunnel entrance) is located at the front edge (ie, the front) of the landslide body, and the infiltration of surface water makes the water content of the new loess higher , the slope of the tunnel entrance and the excavation of the open tunnel cannot guarantee its stability, and landslides are extremely prone to occur; third, when the tunnel dark tunnel passes through the landslide body, it is easy to cause disturbance to the landslide body during the excavation operation, so that the tunnel body is in contact with the landslide Under the interaction of different bodies, dislocation will be generated, which will lead to the destruction of the tunnel structure; fourthly, after the excavation of the tunnel body, the water on both sides of the tunnel body will flow to the tunnel body for discharge. shift
In addition, due to the special mechanical properties and structural characteristics of loess, the poor stability and low bearing capacity of surrounding rock have become the main problems faced by loess tunnel construction

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Construction Method of Loess Tunnel Through Landslide
  • Construction Method of Loess Tunnel Through Landslide
  • Construction Method of Loess Tunnel Through Landslide

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0135] Such as figure 1 A kind of construction method of the loess tunnel passing through the landslide is shown, the tunnel 49 side of the loess tunnel constructed is provided with a tunnel inclined shaft 50, the length of the tunnel 49 is greater than 1500m and its excavation section is greater than 100m 2 , see figure 2 The main hole 49 of the tunnel is a straight tunnel, and the main hole 49 of the tunnel is divided into the tunnel entrance section 10, the tunnel exit section 57 and the middle connection between the tunnel entrance section 10 and the tunnel exit section 57 Section, the inclined shaft 50 of the tunnel intersects with the middle connecting section and the intersection between them is the inclined shaft intersection, the middle connecting section is the auxiliary construction section of the inclined shaft and it takes the inclined shaft intersection as the The boundary is divided into an inclined shaft auxiliary construction entrance section 58 and an incli...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a construction method for a loess tunnel passing through a landslide body. The tunnel entrance section and the tunnel exit section are constructed at the same time; while the tunnel entrance section and the tunnel exit section are being constructed, the inclined The entrance section of auxiliary construction of well and the exit section of auxiliary construction of inclined shaft shall be constructed. The invention is reasonable in design, simple in construction and good in use effect. Before excavation, cement-soil mixing piles are used to reinforce the loess layer in the construction area where the entrance section of the tunnel is located, and effectively limit the length and depth of reinforcement. The loose soil in the tunnel body is consolidated to ensure the safety and reliability of the construction process at the entrance section of the tunnel passing through the landslide. The construction process of the loess tunnel can be quickly completed, and the stability of the excavated tunnel hole can be effectively improved.

Description

technical field [0001] The invention belongs to the technical field of tunnel construction, in particular to a construction method for loess tunnels passing through landslide bodies. Background technique [0002] Loess refers to sediments of yellow silt transported by wind during the Quaternary period in the geological era. Loess collapsibility coefficient (also called collapsibility coefficient) is a mechanical parameter to evaluate the collapsibility of loess. Under a certain pressure, loess collapsibility coefficient refers to the ratio of the difference between the height of the soil sample before and after soaking in water and the original height of the soil sample. The collapsibility coefficient of loess is an important index to evaluate the collapsibility of loess, which can be directly measured by experiment. According to the different collapsibility coefficient of loess, loess can be divided into collapsible loess and non-collapsible loess. Among them, non-collaps...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): E21D9/02E21D9/04E21D9/14E21D11/10E02D5/46
CPCE02D5/46E21D9/02E21D9/04E21D9/14E21D11/105E21D11/107
Inventor 谢江胜梁永峰郭尚坤马传明刘之涛郭瑞张会安曹运祥王建军申运涛葛亮亮赵卫吴小波张博
Owner CHINA RAILWAY 20 BUREAU GRP CORP LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products