Sliding bedding sandy mudstone slope treatment technology
A bed-sliding and sliding technology, which is applied in construction, excavation, and foundation structure engineering, can solve problems such as settlement and structural damage of surrounding buildings, easy collapse of slopes, and infeasibility of traditional techniques, so as to ensure construction progress, The effect of removing the slope collapse and saving the owner's investment
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0047] Such as Figure 1-2 As shown, the treatment technology for slipping bedding sandy mudstone slopes uses anti-slide piles 1 to protect and treat bedding sandy mudstone slopes 2 that have slipped or may slip, specifically including the following steps:
[0048] S1, exploration and preparation, collecting slope 2 data, setting protective measures, determining the position of anti-slide pile 1, and determining the design lock elevation α and the actual construction lock elevation β;
[0049] S2, lock 12 construction, directly carry out lock 12 construction at the actual construction lock elevation β;
[0050]S3, pile body 11 construction, select the material of pile body 11 and the length of pile body 11 according to slope 2 data, and carry out pile body 11 construction;
[0051] S4, excavate and set slope, excavate the side slope 2, and dig down the side slope 2 at the anti-slide pile 1 to the design lock elevation α;
[0052] S5, repairing the anti-slide pile 1, removing...
Embodiment 2
[0078] This embodiment is a further improvement of the previous embodiment, such as Figure 1-2 As shown, the treatment technology for slipping bedding sandy mudstone slopes uses anti-slide piles 1 to protect and treat bedding sandy mudstone slopes 2 that have slipped or may slip, specifically including the following steps:
[0079] S1, exploration and preparation, collecting slope 2 data, setting protective measures, determining the position of anti-slide pile 1, and determining the design lock elevation α and the actual construction lock elevation β;
[0080] S2, lock 12 construction, directly carry out lock 12 construction at the actual construction lock elevation β;
[0081] S3, pile body 11 construction, select the material of pile body 11 and the length of pile body 11 according to slope 2 data, and carry out pile body 11 construction;
[0082] S4, excavate and set slope, excavate the side slope 2, and dig down the side slope 2 at the anti-slide pile 1 to the design loc...
PUM

Abstract
Description
Claims
Application Information

- Generate Ideas
- Intellectual Property
- Life Sciences
- Materials
- Tech Scout
- Unparalleled Data Quality
- Higher Quality Content
- 60% Fewer Hallucinations
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2025 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com