Construction method of highway pavement structure
A technology of pavement structure and construction method, which is applied in the direction of roads, roads, road repairs, etc. It can solve problems such as easy cracks on the road surface, poor drainage of the road surface, and the impact of road use, so as to enhance the drainage performance and heat dissipation performance, and facilitate the maintenance of the road surface , Strengthen the effect of anti-deformation ability
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0030] figure 1 The flow chart of the construction method of the highway pavement structure that this embodiment provides, figure 2 for adoption figure 1 For a schematic diagram of the pavement structure of a highway built with the construction method shown, see figure 1 with figure 2 .
[0031] The construction method of the highway pavement structure provided by this embodiment can be well applied to the construction of semi-rigid bases and sub-bases of roads of all grades, especially for the construction of semi-rigid bases of rural roads, which includes the following steps:
[0032] S1. Laying cushion: Lay a geosynthetic isolation layer on the roadbed, lay gravel and lime cinder on the geosynthetic isolation layer to form a cushion, and lay the cushion to the same width as the roadbed.
[0033] Such as Figure II The highway pavement shown is composed of a cushion layer 1, a base layer 2 and a surface layer 3. The cushion layer 1 is arranged at the bottom of the roa...
Embodiment 2
[0049] figure 1 The flow chart of the construction method of the highway pavement structure that this embodiment provides, figure 2 for adoption figure 1 For a schematic diagram of the pavement structure of a highway built with the construction method shown, see figure 1 with figure 2 .
[0050] The construction method of the highway pavement structure provided by this embodiment can be well applied to the construction of semi-rigid bases and sub-bases of roads of all grades, especially for the construction of semi-rigid bases of rural roads, which includes the following steps:
[0051] S1. Laying cushion: Lay a geosynthetic isolation layer on the roadbed, lay gravel and lime cinder on the geosynthetic isolation layer to form a cushion, and lay the cushion to the same width as the roadbed.
[0052] Such as Figure II The highway pavement shown is composed of a cushion layer 1, a base layer 2 and a surface layer 3. The cushion layer 1 is arranged at the bottom of the roa...
PUM
| Property | Measurement | Unit |
|---|---|---|
| thickness | aaaaa | aaaaa |
| thickness | aaaaa | aaaaa |
| thickness | aaaaa | aaaaa |