Construction method of large-diameter concrete filled steel tube variable-diameter pile foundation

A technology of steel pipe concrete and construction methods, which is applied in the fields of earthwork drilling, infrastructure engineering, drilling equipment and methods, etc., and can solve the problems of rising construction costs and low drilling speed

Active Publication Date: 2022-03-01
CHINA RAILWAY MAJOR BRIDGE ENG GRP CO LTD
View PDF6 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0005] The embodiment of the present application provides a construction method for large-diameter concrete-filled steel pipe variable-diameter pile foundations to solve the problem of the low drilling speed of the rotary drilling rig in the related art after entering the hard rock formation, which leads to a significant increase in the construction cost of the rotary drilling rig in the rock entry stage. The problem

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Construction method of large-diameter concrete filled steel tube variable-diameter pile foundation
  • Construction method of large-diameter concrete filled steel tube variable-diameter pile foundation

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0040] In order to make the purposes, technical solutions and advantages of the embodiments of the present application clearer, the technical solutions in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments It is a part of the embodiments of this application, but not all of them. Based on the embodiments in the present application, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the protection scope of the present application.

[0041] The embodiment of the present application provides a large-diameter concrete-filled steel tube variable-diameter pile foundation construction method, which can solve the problem of low drilling speed after the rotary drilling rig enters the hard rock formation in the related art, which leads to the construction cost of the rotary ...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention relates to a construction method for a large-diameter concrete-filled steel tube variable-diameter pile foundation, which comprises the following steps of: sequentially performing equal-diameter drilling on an upper pile hole, and heightening a steel tube pile after the upper pile hole is drilled by a set depth; the middle pile hole is located in the bottom of the upper pile hole and located in the rock stratum, and the drilling machine conducts graded hole expanding drilling from inside to outside through a drilling bucket with the diameter increasing in sequence; the lower pile hole is subjected to blasting and slag removal, the lower pile hole is located in the bottom of the middle pile hole and located in the bed rock, a plurality of blasting holes are drilled downwards in the hole bottom of the middle pile hole, explosives are buried in the blasting holes, loose blasting is conducted, and a drilling machine drills holes and removes slag till the set hole depth is reached. According to the construction method, according to the geological condition that the upper portion of the pile hole is soft and the lower portion of the pile hole is hard, upper pile hole equal-diameter drilling, middle pile hole chambering drilling and lower pile hole blasting are sequentially adopted for step-by-step drilling construction, the utilization rate of a drilling machine is increased, the hole forming efficiency of the pile hole is improved, and the pile foundation construction cost is reduced.

Description

technical field [0001] The present application relates to the technical field of bridge foundation construction, in particular to a construction method for a large-diameter concrete-filled steel tube variable-diameter pile foundation. Background technique [0002] With the continuous development of railways, highways and urban high-rise buildings, due to the continuous improvement of the bearing capacity of pile foundations, the diameter and depth of pile foundations are becoming larger and larger. to weathered rock formations. Large-diameter rock-socketed bored piles have become the preferred type of foundation engineering and are increasingly used in production. How to ensure the engineering quality and schedule of large-diameter rock-socketed bored piles and control costs during construction has become a problem that must be faced in the construction of large-diameter rock-socketed bored piles. [0003] During the construction of bored piles, the rotary drilling rig has...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): E02D5/38E02D5/48E02D13/08E02D5/66E21B7/28E21B11/04
CPCE02D5/38E02D5/48E02D13/08E02D5/665E21B7/28E21B11/04
Inventor 李艳哲查道宏刘荣程方宏杨大瑜林细弟伍艺张露李鑫黄培白小明赵万超刘恒柱梁金峰余文志
Owner CHINA RAILWAY MAJOR BRIDGE ENG GRP CO LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products