A construction method and technology of composite beams, applied in bridge construction, bridges, bridge parts, etc., can solve problems such as poor subgrade strength, cumbersome erection methods, and inconvenience in coordinated bridge erection, so as to avoid secondary repairs and improve bearing capacity. Effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment
[0044] The present invention provides following technical scheme: comprise the following steps:
[0045] S1: Construction and placement of the bridge support base;
[0046] The first step: site preparation, the bridge erecting machine needs to be spliced at the bridgehead subgrade, and the subgrade needs to be flat and dense to meet the installation load standard of the bridge erecting machine;
[0047] The second step: the compaction treatment of the subgrade. First, the bridge subgrade is generally composed of subgrade, road surface, bridge, tunnel engineering and traffic engineering facilities. The subgrade can be a linear structure built with soil or stone. The preparation materials are: earth and stone powder materials. In order to prevent water from entering the roadbed, cement reinforced concrete aggregates with good rigidity can be used to ensure the force compaction on the bridge roadbed. At the same time, combined with sand and stone filler coating It can be used ...