A reinforced concrete and reinforced structure technology, which is applied in the direction of bridge reinforcement, arch bridges, bridges, etc., can solve the problems of traffic conditions under the bridge, long cost recovery cycle, high working hours consumption, etc., to reduce the overall labor intensity, reduce the overall working hours, improve The effect of compressive capacity
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0026] see Figure 1-6 , a reinforcement structure for the main arch ring of a reinforced concrete arch bridge, which includes a prefabricated concrete surface formwork 2 extending along the axial direction of the concrete main arch ring 1 of the arch bridge, and the surface formwork 2 is composed of several formwork sections 16, said The template working section 16 is a formwork system composed of a circle of interconnected templates. The middle part of the top surface of the template working section 16 is fixed with a first steel anchor box 7, and the middle part of its bottom surface is fixed with a second steel anchor box 8. The first steel anchor box 7 and the second steel anchor box 8 are arranged symmetrically to each other, and the first steel anchor box 7 and the second steel anchor box 8 are passed through the first prestressed steel strand 9 and the second prestress The steel strand 10 tightens and fixes the surface formwork section 16 as a whole. The formwork secti...
Embodiment 2
[0039] see Figure 1-6 , a construction method for reinforcing the main arch ring of a reinforced concrete arch bridge, which is realized through the following steps:
[0040] 1) Clean up the damaged concrete surface of the concrete main arch ring 1 of the arch bridge, roughen the surface, and plant shear pins 3 to ensure that the old and new concrete work together;
[0041] 2) Find out the center line of the top and bottom surfaces of each formwork section 16 of the arch bridge concrete main arch ring 1, and then implant threaded steel bars 17 on the upper top surface and lower bottom surface of the center line of the arch bridge concrete main arch ring 1 working section, and then pass the threaded steel bars Fix the pre-embedded load-bearing plate, weld and fix the force-transmitting steel plate 231 in the first steel anchor box 7 or the second steel anchor box 8 and the load-bearing plate (finally pouring concrete to wrap the first steel anchor box 7 or the second steel anc...