Method for treating large fully filled karst cave provided with deep cave body and excavating tunnel
A technology for excavating large-scale karst caves and tunnels. It is applied in the direction of tunnels, tunnel linings, and earthwork drilling and mining. It can solve the problems of frequent conversion of construction procedures, inconvenient mechanical construction, and adjustment of closing time, so as to facilitate the conversion of construction procedures and high promotion. Effect of applying value, adjusting closure time
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0029] Examples see Figure 1-3 The tunnel to be excavated is shown as a karst tunnel with a maximum span of 18 meters. The left half needs to pass through a large karst cave that is deeply dredged and filled. The construction steps of karst cave treatment and tunnel excavation method are as follows:
[0030] Step one, see Figure 1-2 As shown, when the tunnel to be excavated needs to pass through the cave and be dredged and filled with a large karst cave, support piers should be set in groups at the front and rear of the bottom of the tunnel to be excavated, and the front support pier 1 is located at the 2, the rear buttress 3 is located within the filling 4 or surrounding rock 16 of the large karst cave; at least two groups of buttresses are arranged, which are respectively located below the positions of the initial support side walls on both sides of the tunnel.
[0031] Step two, see Figure 1-2 As shown, between each group of corresponding front pier 1 and rear pier 3,...