Leaking stoppage grouting method for cracks under high pressure flowing water state

A crack and high-pressure technology, which is applied in the field of crack plugging and grouting under high-pressure dynamic water conditions, can solve the problems of inability to form effective seal cracks, ineffective grouting, and ineffective treatment effects, etc.

Active Publication Date: 2017-02-08
SINOHYDRO BUREAU 11 CO LTD
View PDF5 Cites 15 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0006] 1. The seepage pressure of construction joints and cold construction joints is high, but the amount of grouting injection is not large. After grouting, the phenomenon of water leakage on the joint surface still exists, and the treatment effect is not obvious; 2. When the leakage point is drilled and grouted, once the pressure reaches the specified grouting pressure , significantly increased micro-leakage small cracks were found around the grouting holes, and water seepage also appeared in cold construction joints; 3. The seepage pressure at the seepage point is high, and the grouting pressure slightly higher than the water head is still not effective for grouting, and some holes are even basically No grout suction; 4...

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Examples

Experimental program
Comparison scheme
Effect test

Embodiment

[0024] The present invention provides a crack plugging and grouting method under high pressure and dynamic water conditions, which includes the following steps:

[0025] Step 1: Treat cracks: If the width of the crack is less than 0.4mm, use a wire brush tool to remove the contaminants on the crack surface, clean it with an organic solution and keep it dry; if the width of the crack is greater than 0.4mm, use a steel drill or a pneumatic pick The cracks are cut into V-shaped grooves. When cutting the grooves, they are first opened along the cracks, and then widened to both sides. After chiseling, use a wire brush and compressed air to remove the concrete debris and dust, and use epoxy mortar to seal;

[0026] Step 2: Drilling: If the width of the crack exceeds 0.4mm, set oblique holes on both sides of the crack. The intersection of the drilled hole and the crack serves as the grouting hole for the crack grouting. Before the crack is grouted, check the area that affects the leakage o...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention relates to the technical field of grouting repairing of concrete cracks of a hydraulic building, in particular to a leaking stoppage grouting method for cracks under a high pressure flowing water state. The method comprises the following steps: processing the cracks, drilling, configuring grout, grouting and ending. The method according to the invention adopts a construction method of grouting one hole and depressurizing peripheral holes, the condition that contact cracks between the cracks and surrounding rocks cannot be entered by adopting a conventional means is changed, and grout can enter into the contact cracks to be settled and solidified smoothly, such that the leakage cracks are closed and the aim of leaking stoppage of the cracks is realized; the method according to the invention adopts a cement-base slurry material adopting taking a mixed material of cement slurry, gypsum powder and silicon powder as a main agent, when the grout enters into the contact cracks between the concrete and the surrounding rocks, due to the characteristics of slow flow speed and fake solidification of the grout, water seepage pressure cannot discharge the grout after the grout enters into the contact cracks, such that such type of slurry material can be quickly settled and solidified, and the aim of leakage stoppage of the cracks is realized.

Description

Technical field [0001] The invention relates to the technical field of concrete crack grouting repair for hydraulic structures, in particular to a crack plugging and grouting method under high pressure and dynamic water conditions. Background technique [0002] The crack grouting method is mainly used for the repair of concrete cracks that affect the integrity of the structure or require anti-seepage. Pressure equipment is used to press the cementing material into the cracks of the concrete. After the cementing material is hardened, it forms a whole with the concrete, thereby sealing The purpose of blocking reinforcement. Commonly used cementing materials are cement paste, epoxy resin, methacrylate, polyurethane and other chemical materials. [0003] Concrete crack grouting is usually carried out by drilling buried pipes or drilling buried nozzles. According to the thickness and crack depth of the concrete structure, the method of drilling is usually used to arrange the inclined h...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
IPC IPC(8): E02B3/16
CPCE02B3/16
Inventor 陈敦刚
Owner SINOHYDRO BUREAU 11 CO LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products