Construction method and special guard screen for static demolition and home position reconstruction of overpass bridge

A construction method and technology for a flyover bridge, which are applied in the field of static demolition and in-situ reconstruction of highway widening flyover bridges, can solve the problems of large surrounding disturbance, poor environmental protection, and large amount of on-site garbage cleaning, and achieve the effect of ensuring double safety.

Pending Publication Date: 2017-10-20
ZHEJIANG COMM CONSTR GRP CO LTD
View PDF8 Cites 11 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0005] The purpose of the present invention is to provide a construction method for the static dismantling and in-situ reconstruction of the overpass bridge and its special protective net. In the dismantling method of the existing bridge, the existing noise disturbs the surrounding area greatly, the amount of on-site garbage cleaning is large, and it is environmentally friendly. It also solves the technical problem that the construction surface is covered with the entire road in the existing bridge demolition method, a large number of machines are used, and the technical problem that the construction of the highway under the bridge cannot be satisfied while opening to traffic

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Construction method and special guard screen for static demolition and home position reconstruction of overpass bridge
  • Construction method and special guard screen for static demolition and home position reconstruction of overpass bridge
  • Construction method and special guard screen for static demolition and home position reconstruction of overpass bridge

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0096] Examples see figure 1 As shown, a method for static demolition and in-situ reconstruction of simply supported beam bridges widening and spanning highways, the construction steps are as follows:

[0097] Step 1, general preparation before construction;

[0098] The overpass bridge to be demolished and reconstructed in situ is a two-span simply supported girder bridge. There is a central divider 1 and a two-way expressway roadway under the bridge body. The pier 2 is located on the central divider. The bridge body includes the first span bridge body 3 and the second bridge body 4 correspond to the first expressway carriageway 5 and the second expressway carriageway 6 below, and according to the field conditions and structural parameters of the overpass bridge, a method of statically dismantling the old bridge by span is proposed and methods for in situ reconstruction of new bridges.

[0099] Step 2, demolition of the old bridge structure;

[0100] Step A is designed to ...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention relates to a construction method and a special guard screen for static demolition and home position reconstruction of an overpass bridge. A static demolition method comprises the following steps of performing mid-span bridge surface separation; performing hoisting hole arrangement, blocking, symmetric cutting and hoisting away on anti-collision walls on two sides; performing hoisting hole arrangement and hinging crack cutting and separation on same-span simply supported beams; and performing sequential hanging away one by one from left to right or from right to left and the like. A home position reconstruction method comprises the following steps of constructing stand columns and bent caps, constructing beam plates, constructing auxiliary engineering, and the like. According to the construction method disclosed by the invention, the structure of the overpass bridge is demolished according to the requirement that the traffic is not interrupted, a method comprising the following steps of determining the sequence of demolishing the bridge and separating spans, blocking and cutting anti-collision guardrails, and cutting and lifting a main beam is adopted, so that beam members are cut into blocks, are hoisted by a crane, and can be directly transported away by a transporting vehicle; the method is high in civil construction degree, simple and easy to operate, wide in application range, and easy to popularize; the situation that passing under the overpass bridge and the construction are safe is guaranteed; during construction, the situation that passing of the highway is smooth and safe is guaranteed; the civil construction degree is high; and the construction method has good social benefits and economic benefits.

Description

technical field [0001] The invention relates to the technical field of expressway widening, in particular to a method for statically dismantling and in-situ reconstruction of an expressway widening flyover. Background technique [0002] With the rapid development of the economy, it is imperative to widen the expressway, and the corresponding overpasses, separation bridges, etc. have flyovers, which will inevitably face the problem of demolition, displacement or in-situ reconstruction. At present, the demolition methods of existing bridges mainly include on-site mechanical crushing method, block-cutting method of full support, segmental dismantling method of cantilever of bridge erecting machine, directional blasting method and overall jacking method, etc. Requirements for road traffic and construction while opening to traffic. [0003] The existing mechanical crushing method and directional blasting method have the advantages of fast construction speed, but both have the di...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): E01D24/00E01D21/08E01C1/02
CPCE01C1/02E01D21/08E01D22/00
Inventor 李嘉朱文喜姚磊梁超于超
Owner ZHEJIANG COMM CONSTR GRP CO LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products