Fast construction method for embedded turnout system
A construction method and embedded technology, applied in the directions of roads, tracks, buildings, etc., can solve problems such as the description of the construction method of the embedded track turnout system, and achieve the effect of facilitating later maintenance.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment
[0034] Example: such as image 3 As shown, a rapid construction method for an embedded turnout system includes the following steps:
[0035] 1) Construction preparation: use CPIII laying-out method for setting out and CPIII control network for measurement, then pour the base 1 at the construction site, mark the center line of the line, the outline of the turnout plate 4 and the outline of the plate seam 43 on the top surface of the base 1, and An isolation layer 2 is laid on the top surface of the base 1 . In step 1), use the CPIII control network setting method to stake out the position of the sideline of the base 1 and determine the installation position of the steel bars, then bind the steel bars, use the baffle to close the mold of the base 1, pour concrete, and the strength of the concrete reaches the design strength of 75 %, remove the template; use the CPIII control network to stake out and mark the center line of the line, the outline position of the turnout plate 4 a...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com