A design method and construction technology of a "human"-shaped ground well in a coal mining area
A design method and mining area technology, applied in the direction of drilling equipment and methods, mining equipment, drilling equipment, etc., can solve the problems of small gas area, small drainage range of construction vertical wells in mining area, and large number of construction wells, etc. Achieve the effects of reducing drilling costs, facilitating centralized management, and improving the recovery rate of gas resources
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0073] A method for designing a "human"-shaped surface well in a coal mining area. The surface well includes a vertical well section 1 and a horizontal well section 3, and the vertical well section 1 and the horizontal well section 3 are connected through an arc-shaped well section 2; The well location is determined by the air return roadway and the overlying strata. The distance a between the well position and the production stop line is 150m to 200m. The roadway distance b is 1 / 5 of the inclination length of the coal mining face, in which the key layer refers to the overlying strata with strength ≥ 60MPa, stiffness ≥ 25Gpa, and thickness ≥ 6m; the well depth of vertical well section 1 is below the coal seam floor and above the fracture zone, The lateral casing 6 that is easy to penetrate laterally is set at the depth position of the vertical well section from the surface wellhead h3; through the drilling of the vertical well section 1, the actual coal seam burial depth, coal ...
Embodiment 2
[0078] A construction technique for a "man"-shaped surface well in a coal mining area, first drilling a vertical well section 1, then drilling an arc-shaped well section 2, and finally drilling a horizontal well section 3, comprising the following steps:
[0079] S1 Determining the well location: determine the well location according to the stop production line, the return airway and the overlying strata. The well position is located at the intersection of the bottom of the overlying strata key layer and the elliptical zone of the overlying strata fissure, and is located at a distance of 150m to 200m from the stop production line a within the area.
[0080] S2 drilling vertical section 1:
[0081] S2.1 First opening: Drill to 10m below the topsoil layer, next casing 4 cementing;
[0082] S2.2 second opening:
[0083] S2.21 Drilling to 5-10m above the bottom of the bent subsidence zone of the overlying rock;
[0084] S2.22 Run the second casing 5 for cementing, and set the l...