A technology for wind turbines and DC cables, applied in the installation of cables, cable installation devices, wind turbines, etc., can solve the problems of insufficient stability of cables, high labor intensity, long operation time, etc., and achieves simple structure, high work efficiency, and reduced effect of stress
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment 1
[0041] A method for installing DC cables in a wind turbine nacelle, comprising the following steps:
[0042] Step 1, place the cable drum at the rear of the cabin, pull the head of a cable from the cable drum to the cable ladder, and then guide the cable through the rollers on the cable ladder, and pull the cable from the cabin to the The duct of the tower is pulled to the duct end of the engine room, which effectively reduces the difficulty of installation, thereby reducing the time consumption and cost of installation;
[0043] Step 2. When the cables are all pulled out from the cable reel, place the cables on the cable ladder, making sure there are more cables than required so that there is enough room for the cables below the inverter end on the machine side, Facilitate follow-up operations;
[0044] Step 3, connect the cable lug at the inverter side of the machine to the bus bar system, and then install the EMC clip on the cable;
[0045] Step 4, continue to pull the ca...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com