Arch-first and beam-second construction method for bracket-free tied arch

A technology of arch first and beam later and construction method, which is applied in the direction of erection/assembly of bridges, bridges, bridge construction, etc., and can solve the problem of limited bearing capacity of steel pipe rods of full hall brackets, high requirements for foundation bearing capacity, and high requirements for pouring quality control measures, etc. problems, to achieve the effect of meeting the structural installation quality, ensuring the navigation requirements, widely promoting the application value and reference significance
CN112554067AInactive Publication Date: 2021-03-26浙江省建投交通基础建设集团有限公司

Patent Information

Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
浙江省建投交通基础建设集团有限公司
Publication Date
2021-03-26
Estimated Expiration
Not applicable · inactive patent

Smart Images

  • Figure 1
    Figure 1
  • Figure 2
    Figure 2
  • Figure 3
    Figure 3
Patent Text Reader

Abstract

The invention discloses an arch-first and beam-second construction method for a bracket-free tied arch, and belongs to the technical field of building construction. The method comprises the followingsteps: 1, transporting arch ribs; 2, pre-burying arch ribs of arch foot sections; 3, temporarily solidifying the arch feet and the bridge piers; 4, penetrating a temporary cable for construction: pulling the temporary cable to the cross beam at the mounting end, fixing the temporary cable through an anchorage device, and circularly constructing and penetrating the cable until the end; 5, hoistingarch ribs; 6, mounting a wind brace; 7, performing pressure injection on arch rib concrete; 8, performing suspender prestressed cable construction; 9, mounting a tie beam and a middle cross beam; 10,installing prefabricated bridge decks, bridge deck pavement and anti-collision guardrails; and 11, adjusting the cable force of the finished bridge suspender. By the adoption of the construction method, the construction period is shortened, and the labor intensity of workers is reduced; and the navigation requirement is guaranteed during construction, the balance of stress changes in arch structure construction is effectively guaranteed, the safety of bridge construction and later operation is guaranteed, the ecological environment is protected, and wide application and popularization value and reference significance are achieved.
Need to check novelty before this filing date? Find Prior Art

Description

technical field

[0001] The invention belongs to the technical field of building construction, and in particular relates to a construction method of a bracketless tie rod arch first arch and then beam. Background technique

[0002] The traditional support method construction starts from the ground and builds the steel pipe support to the vault, and then carries out formwork, pouring, maintenance and other constructions. The biggest advantage of this method is that it does not require large-scale hoisting equipment, and its disadvantage is the consumption of support formwork for construction. Large, long construction period, large investment of manpower, steel pipe support erection requires high bearing capacity of the foundation, and the bearing capacity of the steel pipe rod of the conventional full hall support is limited, and the safety risk is relatively large. For large-volume concrete structures, pouring in sections and blocks There are many, high requirements for pouri...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine